Bottling, Canning & Filling Lines worked example
Filler OEE at 99% filler speed performance vs rated speed: a worked example
What does the result look like when filler speed performance vs rated speed reaches 99%? The full calculation is worked below with real intermediate numbers. a filler is being reviewed for downtime, speed loss, low fills, high fills, foam, valve problems, or rejected packages
The inputs for this scenario
- Filler operating (run) time this shift: 6.8 hr (unchanged)
- Planned filler production time: 8 hr (unchanged)
- Filler speed performance vs rated speed: 99 % (raised for this scenario; the documented default is 91)
- Good-fill quality rate after rejects: 98 % (unchanged)
Working through the calculation
- Applying the documented formula (Filler availability = filler operating time ÷ planned filler production time) to the inputs above produces each figure below.
- At this operating point the engine returns 82.47 % OEE for filler oee, the number this scenario is built around.
- At this operating point the engine returns 85 % for filler availability.
- At this operating point the engine returns 99 % for filler speed performance versus standard.
- At this operating point the engine returns 98 % for good-fill quality after low-fill and high-fill rejects.
How this compares with the baseline
- Against the tool's baseline example, where filler speed performance vs rated speed sits at 91% and the headline result is 75.8 % OEE, this scenario comes in 8.79% above the baseline at 82.47 % OEE.
- A figure at this level is achievable when filler speed performance vs rated speed is genuinely sustained, not just peaked for a shift. OEE alone cannot tell you why a loss occurred — an 85% availability could be one long jam or twenty micro-stops, which need very different fixes, so always pair it with a downtime Pareto.
Results at a glance
- Filler OEE: 82.47 % OEE (headline result)
- Filler availability: 85 %
- Filler speed performance versus standard: 99 %
- Good-fill quality after low-fill and high-fill rejects: 98 %
Run it with your numbers
- Every input above is editable in the live Filler OEE calculator, which recalculates instantly and can be shared with the inputs intact.
Last reviewed 2026-05-12.