Cathode Active Material & Precursor Manufacturing worked example
Production Ramp Planner at 65% expected ramp uptime: a worked example in cathode active material & precursor manufacturing
This worked example runs the production ramp planner numbers for a tougher week than the baseline: 65% expected ramp uptime instead of the typical 90%. Estimate accepted CAM or precursor output during a production ramp after planned cycles, uptime, and first-pass release yield are applied.
The inputs for this scenario
- Ramp output per production cycle: 4 kg / cycle (held at the documented default)
- Planned ramp cycles: 480 cycles (held at the documented default)
- Expected ramp uptime: 65 % (the input this scenario stresses; the baseline uses 90)
- Expected first-pass release yield: 97 % (held at the documented default)
Working through the calculation
- The calculation starts from the formula this tool documents: Gross ramp production output = ramp output per production cycle × planned ramp cycles.
- Accepted ramp production output works out to 1,211 kg at these inputs, and this is the headline figure for the scenario.
- Gross ramp production output works out to 1,920 kg at these inputs.
- Ramp output lost to downtime works out to 672 kg at these inputs.
- Ramp output held or reworked works out to 37.44 kg at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where expected ramp uptime sits at 90% and the headline result is 1,676 kg, this scenario comes in 27.78% below the baseline at 1,211 kg.
- Use it during ramp planning to set customer-committable volumes, or to test how an uptime or yield improvement changes releasable tonnage. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- Accepted ramp production output: 1,211 kg (headline result)
- Gross ramp production output: 1,920 kg
- Ramp output lost to downtime: 672 kg
- Ramp output held or reworked: 37.44 kg
Run it with your numbers
- To rerun this with your own numbers, open the live Production Ramp Planner calculator, set expected ramp uptime to your actual value, and adjust the remaining inputs to match your operation.
Last reviewed 2026-05-12.