CNC Machining worked example
CNC Program Runtime with in-cut cutting time of 3.75 min: a worked example
This worked example runs the cnc program runtime numbers for a tougher week than the baseline: in-cut cutting time of 3.75 min instead of the typical 7.5 min. Estimate total CNC program runtime by summing cutting time, rapid/non-cutting time, tool-change/probing time, and load or unload allowance.
The inputs for this scenario
- In-cut cutting time: 3.75 min (the input this scenario stresses; the baseline uses 7.5)
- Rapid, approach, and air-cut time: 1.8 min (held at the documented default)
- Tool-change, probing, and in-process inspection time: 1.2 min (held at the documented default)
- Load, unload, and operator handling allowance: 2 min (held at the documented default)
Working through the calculation
- The calculation starts from the formula this tool documents: CNC program runtime = cutting time + rapid, approach, and non-cutting time + tool change, probing, and inspection time + load, unload, and operator allowance.
- estimated CNC program runtime works out to 8.75 min at these inputs, and this is the headline figure for the scenario.
- Element 1 works out to 3.75 min at these inputs.
- Element 2 works out to 1.8 min at these inputs.
- Element 3 + 4 works out to 3.2 min at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where in-cut cutting time sits at 7.5 min and the headline result is 12.5 min, this scenario comes in 30% below the baseline at 8.75 min.
- Use it when quoting a new part, building a routing, or sanity-checking estimated cycle time against machine history. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- estimated CNC program runtime: 8.75 min (headline result)
- Element 1: 3.75 min
- Element 2: 1.8 min
- Element 3 + 4: 3.2 min
Run it with your numbers
- To rerun this with your own numbers, open the live CNC Program Runtime calculator, set in-cut cutting time to your actual value, and adjust the remaining inputs to match your operation.
Last reviewed 2026-05-12.