Construction Machinery & Attachments worked example
Bucket Capacity at 59% machine uptime: a worked example
This worked example runs the bucket capacity numbers for a tougher week than the baseline: 59% machine uptime instead of the typical 82%. Estimate usable bucket production capacity from heaped bucket size, cycles, uptime, and fill efficiency.
The inputs for this scenario
- Heaped bucket capacity per cycle: 1.75 yd³ / cycle (held at the documented default)
- Planned bucket cycles: 52 cycles (held at the documented default)
- Machine uptime: 59 % (the input this scenario stresses; the baseline uses 82)
- Bucket fill & usable material yield: 90 % (held at the documented default)
Working through the calculation
- The calculation starts from the formula this tool documents: Rated bucket volume before losses = heaped bucket capacity per cycle × planned bucket cycles.
- usable bucket volume works out to 48.32 yd³ at these inputs, and this is the headline figure for the scenario.
- rated bucket volume before losses works out to 91 yd³ at these inputs.
- bucket volume lost to downtime works out to 37.31 yd³ at these inputs.
- bucket volume lost to fill factor works out to 5.37 yd³ at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where machine uptime sits at 82% and the headline result is 67.16 yd³, this scenario comes in 28.05% below the baseline at 48.32 yd³.
- Use it when planning earthmoving or loading production, sizing fleets, or setting shift targets for a specific bucket and material. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- usable bucket volume: 48.32 yd³ (headline result)
- rated bucket volume before losses: 91 yd³
- bucket volume lost to downtime: 37.31 yd³
- bucket volume lost to fill factor: 5.37 yd³
Run it with your numbers
- To rerun this with your own numbers, open the live Bucket Capacity calculator, set machine uptime to your actual value, and adjust the remaining inputs to match your operation.