Conveyors worked example
Conveyor ROI with total conveyor project investment of 462,500 $: a worked example
What does the result look like when total conveyor project investment reaches 462,500 $? The full calculation is worked below with real intermediate numbers. a plant manager or project engineer needs a first-pass business case for conveyor or line automation investment
The inputs for this scenario
- Total conveyor project investment: 462,500 $ (raised for this scenario; the documented default is 185,000)
- Annual labor, downtime, and throughput savings: 82,000 $ / yr (unchanged)
- Annual conveyor support cost: 12,000 $ / yr (unchanged)
Working through the calculation
- Applying the documented formula (Net annual savings = annual savings − annual support cost) to the inputs above produces each figure below.
- At this operating point the engine returns 6.61 years for conveyor payback period, the number this scenario is built around.
- At this operating point the engine returns 70,000 $ / yr for net annual savings.
- At this operating point the engine returns 462,500 $ for project investment.
- At this operating point the engine returns -112,500 $ for five-year net benefit.
How this compares with the baseline
- Against the tool's baseline example, where total conveyor project investment sits at 185,000 $ and the headline result is 2.64 years, this scenario comes in 150% above the baseline at 6.61 years.
- A figure at this level is achievable when total conveyor project investment is genuinely sustained, not just peaked for a shift. Simple payback ignores the time value of money, throughput ramp-up, and salvage value, so for long-horizon decisions pair it with an NPV or IRR analysis.
Results at a glance
- Conveyor payback period: 6.61 years (headline result)
- Net annual savings: 70,000 $ / yr
- Project investment: 462,500 $
- Five-year net benefit: -112,500 $
Run it with your numbers
- Every input above is editable in the live Conveyor ROI calculator, which recalculates instantly and can be shared with the inputs intact.
Last reviewed 2026-05-12.