Defense Electronics & Ruggedized Systems worked example

Program Documentation Burden at 12% review, signoff, and correction allowance: a worked example

This scenario runs the program documentation burden calculation on the strong side: 12% review, signoff, and correction allowance, with every other input held at its documented default. Use it when program documentation burden in defense electronics and ruggedized systems is changing rate or allowance and you want to see the impact.

The inputs for this scenario

  • Program data items / DD-1423 records to complete: 120 records (unchanged)
  • Documentation completion pace: 12 records / hr (unchanged)
  • Review, signoff, and correction allowance: 12 % (raised for this scenario; the documented default is 10)

Working through the calculation

  • Applying the documented formula (Base documentation hours = program records to complete รท documentation completion pace) to the inputs above produces each figure below.
  • At this operating point the engine returns 11.2 hr for required documentation hours, the number this scenario is built around.
  • At this operating point the engine returns 10 hr for base documentation hours.
  • At this operating point the engine returns 12 % for review and correction allowance.
  • At this operating point the engine returns 12 pieces / min for documentation completion pace.

How this compares with the baseline

  • Against the tool's baseline example, where review, signoff, and correction allowance sits at 10% and the headline result is 11 hr, this scenario comes in 1.82% above the baseline at 11.2 hr.
  • Use it when staffing the documentation effort for a CDRL-driven deliverable or estimating the data-package tail behind a hardware milestone. Treat this as a target state: the delta against the baseline quantifies what the improvement is worth before you commit to chasing it.

Results at a glance

  • Required documentation hours: 11.2 hr (headline result)
  • Base documentation hours: 10 hr
  • Review and correction allowance: 12 %