Elevators, Escalators & Vertical Transport Equipment worked example
Fixture Install Time at 13% shaft access, wiring, and checkout allowance: a worked example
This worked example runs the fixture install time numbers for a tougher week than the baseline: 13% shaft access, wiring, and checkout allowance instead of the typical 18%. Estimate elevator fixture installation time from landing fixtures, install pace, and field allowance.
The inputs for this scenario
- Car and hall fixtures to install: 44 fixtures (held at the documented default)
- Fixture mount and terminate pace: 5.5 fixtures / hr (held at the documented default)
- Shaft access, wiring, and checkout allowance: 13 % (the input this scenario stresses; the baseline uses 18)
Working through the calculation
- The calculation starts from the formula this tool documents: Base fixture install time = fixtures to install รท fixture installation pace.
- Estimated fixture installation time works out to 9.04 hr at these inputs, and this is the headline figure for the scenario.
- Base fixture install time works out to 8 hr at these inputs.
- Access, wiring, and checkout allowance works out to 13 % at these inputs.
- Fixture installation pace works out to 5.5 fixtures / hr at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where shaft access, wiring, and checkout allowance sits at 18% and the headline result is 9.44 hr, this scenario comes in 4.24% below the baseline at 9.04 hr.
- Use it when planning a fixture rough-in and finish phase, sizing a two- or three-person install crew, or pricing the fixture labor line in a modernization quote. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- Estimated fixture installation time: 9.04 hr (headline result)
- Base fixture install time: 8 hr
- Access, wiring, and checkout allowance: 13 %
- Fixture installation pace: 5.5 fixtures / hr
Run it with your numbers
- To rerun this with your own numbers, open the live Fixture Install Time calculator, set shaft access, wiring, and checkout allowance to your actual value, and adjust the remaining inputs to match your operation.
Last reviewed 2026-05-12.