Finish Booth Capacity at 62% finish booth availability: a worked example
This worked example runs the finish booth capacity numbers for a tougher week than the baseline: 62% finish booth availability instead of the typical 86%. Estimate good finish-booth output for stained, painted, coated, or clear-coated furniture and fixture parts per shift.
The inputs for this scenario
- Finished parts per booth cycle: 24 parts / cycle (held at the documented default)
- Available finish booth cycles: 18 cycles (held at the documented default)
- Finish booth availability: 62 % (the input this scenario stresses; the baseline uses 86)
- First-pass finish yield: 94 % (held at the documented default)
Working through the calculation
- The calculation starts from the formula this tool documents: Gross finish booth capacity = finished parts per booth cycle × available finish booth cycles.
- Good finish booth capacity works out to 252 units at these inputs, and this is the headline figure for the scenario.
- Gross finish booth capacity works out to 432 units at these inputs.
- Finish booth capacity downtime loss works out to 164 units at these inputs.
- Finish booth capacity reject or rework loss works out to 16.07 units at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where finish booth availability sits at 86% and the headline result is 349 units, this scenario comes in 27.91% below the baseline at 252 units.
- Use it when scheduling a finishing line, checking whether finishing is the bottleneck, or quoting lead time on a coated-part order. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- Good finish booth capacity: 252 units (headline result)
- Gross finish booth capacity: 432 units
- Finish booth capacity downtime loss: 164 units
- Finish booth capacity reject or rework loss: 16.07 units