Industrial Equipment, Machinery & Capital Goods worked example

Field Install Cost at 99% quoted installation scope: a worked example in industrial equipment, machinery & capital goods

This scenario runs the field install cost calculation on the strong side: 99% quoted installation scope, with every other input held at its documented default. Use it when pricing rigging, mechanical installation, electrical hookup, leveling, utilities, and production startup support.

The inputs for this scenario

  • Installation crew days: 10 days (unchanged)
  • Loaded install crew cost: 5,200 $ / day (unchanged)
  • Quoted installation scope: 99 % (raised for this scenario; the documented default is 90)
  • Fixed mobilization and rental cost: 12,000 $ (unchanged)

Working through the calculation

  • Applying the documented formula (Variable field install cost = installation crew days × loaded install crew cost × quoted installation scope) to the inputs above produces each figure below.
  • At this operating point the engine returns 63,480 $ for total field install cost, the number this scenario is built around.
  • At this operating point the engine returns 6,348 $ / day for loaded install crew cost.
  • At this operating point the engine returns 51,480 $ for variable field install cost.
  • At this operating point the engine returns 12,000 $ for fixed mobilization and rental cost.

How this compares with the baseline

  • Against the tool's baseline example, where quoted installation scope sits at 90% and the headline result is 58,800 $, this scenario comes in 7.96% above the baseline at 63,480 $.
  • Use it when quoting commissioning and field install for capital equipment, or when reconciling actual install hours against the number you bid. Treat this as a target state: the delta against the baseline quantifies what the improvement is worth before you commit to chasing it.

Results at a glance

  • Total field install cost: 63,480 $ (headline result)
  • Loaded install crew cost: 6,348 $ / day
  • Variable field install cost: 51,480 $
  • Fixed mobilization and rental cost: 12,000 $