Industrial Valves, Actuators & Flow Control worked example
Pressure Test Throughput at 61% test bench availability: a worked example
This worked example runs the pressure test throughput numbers for a tougher week than the baseline: 61% test bench availability instead of the typical 85%. Calculate effective pressure test bench throughput per shift by combining valves per test cycle, available cycles per shift, bench availability, and first-pass test yield.
The inputs for this scenario
- Valves tested per cycle: 2 valves / cycle (held at the documented default)
- Test cycles available per shift: 24 cycles / shift (held at the documented default)
- Test bench availability: 61 % (the input this scenario stresses; the baseline uses 85)
- First-pass test yield: 95 % (held at the documented default)
Working through the calculation
- The calculation starts from the formula this tool documents: Gross throughput = valves per cycle x cycles per shift.
- Effective valves tested per shift (passed) works out to 27.82 valves at these inputs, and this is the headline figure for the scenario.
- Gross valve test throughput per shift works out to 48 valves at these inputs.
- Valves lost to bench downtime works out to 18.72 valves at these inputs.
- Valves lost to first-test failures works out to 1.46 valves at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where test bench availability sits at 85% and the headline result is 38.76 valves, this scenario comes in 28.24% below the baseline at 27.82 valves.
- Use it to size test-bench capacity against production output, justify a second bench, or model how a yield or uptime improvement changes daily passed-valve count. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- Effective valves tested per shift (passed): 27.82 valves (headline result)
- Gross valve test throughput per shift: 48 valves
- Valves lost to bench downtime: 18.72 valves
- Valves lost to first-test failures: 1.46 valves
Run it with your numbers
- To rerun this with your own numbers, open the live Pressure Test Throughput calculator, set test bench availability to your actual value, and adjust the remaining inputs to match your operation.
Last reviewed 2026-05-12.