Metal Recycling, Scrap Processing & Salvage worked example
Scrap Freight Burden at 7.2% setup, tarping, and weigh-in delay allowance: a worked example
This worked example runs the scrap freight burden numbers for a tougher week than the baseline: 7.2% setup, tarping, and weigh-in delay allowance instead of the typical 10%. Estimate scrap freight burden for metal recycling, scrap processing and salvage using production-ready inputs so teams can plan labor hours, schedule the work, or check whether the job fits the available shift time.
The inputs for this scenario
- Tonnage of scrap to haul this shift: 120 units (held at the documented default)
- Loading throughput per loader-minute: 12 units / min (held at the documented default)
- Setup, tarping, and weigh-in delay allowance: 7.2 % (the input this scenario stresses; the baseline uses 10)
Working through the calculation
- The calculation starts from the formula this tool documents: Base scrap freight burden time = scrap freight burden workload รท scrap freight burden completion rate.
- Required scrap freight burden time works out to 10.72 hr at these inputs, and this is the headline figure for the scenario.
- Base scrap freight burden time works out to 10 hr at these inputs.
- Scrap freight burden allowance applied works out to 7.2 % at these inputs.
- Scrap freight burden completion rate works out to 12 pieces / min at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where setup, tarping, and weigh-in delay allowance sits at 10% and the headline result is 11 hr, this scenario comes in 2.55% below the baseline at 10.72 hr.
- Use it when scheduling outbound haulers, sizing a loading crew for a peak buying day, or quoting how long a dedicated trailer will be tied up at your yard. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- Required scrap freight burden time: 10.72 hr (headline result)
- Base scrap freight burden time: 10 hr
- Scrap freight burden allowance applied: 7.2 %
- Scrap freight burden completion rate: 12 pieces / min
Run it with your numbers
- To rerun this with your own numbers, open the live Scrap Freight Burden calculator, set setup, tarping, and weigh-in delay allowance to your actual value, and adjust the remaining inputs to match your operation.
Last reviewed 2026-05-12.