Oil, Gas & Energy Equipment Manufacturing worked example
Skid Assembly Labor at 7.2% fit-up, staging, and rigging allowance: a worked example
This worked example runs the skid assembly labor numbers for a tougher week than the baseline: 7.2% fit-up, staging, and rigging allowance instead of the typical 10%. Estimate skid assembly labor hours from the number of components and connections on the skid, the crew assembly rate, and an allowance for fit-up, staging, and rigging, so fabrication managers can schedule the build and confirm it fits the available shift time.
The inputs for this scenario
- Components and connections to assemble: 120 units (held at the documented default)
- Crew assembly rate: 12 units / min (held at the documented default)
- Fit-up, staging, and rigging allowance: 7.2 % (the input this scenario stresses; the baseline uses 10)
Working through the calculation
- The calculation starts from the formula this tool documents: Base skid assembly time = components and connections to assemble รท crew assembly rate.
- Required skid assembly labor works out to 10.72 hr at these inputs, and this is the headline figure for the scenario.
- Base skid assembly time works out to 10 hr at these inputs.
- Fit-up and staging allowance applied works out to 7.2 % at these inputs.
- Crew assembly rate works out to 12 pieces / min at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where fit-up, staging, and rigging allowance sits at 10% and the headline result is 11 hr, this scenario comes in 2.55% below the baseline at 10.72 hr.
- Use it when quoting a skid package, loading the assembly cell for the week, or checking whether your committed labor hours match the bill of materials. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- Required skid assembly labor: 10.72 hr (headline result)
- Base skid assembly time: 10 hr
- Fit-up and staging allowance applied: 7.2 %
- Crew assembly rate: 12 pieces / min