Finishing worked example
Thermal Cure Schedule with ramp-up time to cure temperature of 5 min: a worked example
This worked example runs the thermal cure schedule numbers for a tougher week than the baseline: ramp-up time to cure temperature of 5 min instead of the typical 10 min. Add ramp, soak, dwell, and cool-down times for a coating cure schedule.
The inputs for this scenario
- Ramp-up time to cure temperature: 5 min (the input this scenario stresses; the baseline uses 10)
- Soak time at cure temperature: 8 min (held at the documented default)
- Additional oven dwell: 6 min (held at the documented default)
- Cool-down time: 4 min (held at the documented default)
Working through the calculation
- The calculation starts from the formula this tool documents: Total = sum of entered elements.
- Total works out to 23 min at these inputs, and this is the headline figure for the scenario.
- Element 1 works out to 5 min at these inputs.
- Element 2 works out to 8 min at these inputs.
- Element 3 + 4 works out to 10 min at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where ramp-up time to cure temperature sits at 10 min and the headline result is 28 min, this scenario comes in 17.86% below the baseline at 23 min.
- Use it to plan batch turnaround, set conveyor takt, or document a standard cure recipe for a specific powder and part. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- Total: 23 min (headline result)
- Element 1: 5 min
- Element 2: 8 min
- Element 3 + 4: 10 min
Run it with your numbers
- To rerun this with your own numbers, open the live Thermal Cure Schedule calculator, set ramp-up time to cure temperature to your actual value, and adjust the remaining inputs to match your operation.
Last reviewed 2026-05-12.