PPE & Infection Control Products worked example
Raw Material Buffer with nonwoven and polymer feedstock consumed per day of 3,000 units / day: a worked example
This scenario runs the raw material buffer calculation on the strong side: nonwoven and polymer feedstock consumed per day of 3,000 units / day, with every other input held at its documented default. Use it when raw material buffer in ppe and infection control products is being sized for a buffer or safety stock review.
The inputs for this scenario
- Nonwoven / polymer feedstock consumed per day: 3,000 units / day (raised for this scenario; the documented default is 1,200)
- Resin & media replenishment lead time: 85 days (unchanged)
- Safety stock coverage multiplier: 1.1 units (unchanged)
Working through the calculation
- Applying the documented formula (Raw material buffer cycle stock = raw material buffer daily usage × raw material buffer lead time) to the inputs above produces each figure below.
- At this operating point the engine returns 32.09 days for protected days of supply, the number this scenario is built around.
- At this operating point the engine returns 35.29 days for unprotected days.
- At this operating point the engine returns 3,000 pieces for inventory.
- At this operating point the engine returns 85 pieces / day for daily usage.
How this compares with the baseline
- Against the tool's baseline example, where nonwoven and polymer feedstock consumed per day sits at 1,200 units / day and the headline result is 12.83 days, this scenario comes in 150% above the baseline at 32.09 days.
- Use it when setting reorder points and minimum on-hand quantities for critical PPE feedstocks, or when stress-testing coverage ahead of a demand surge or supplier allocation. Treat this as a target state: the delta against the baseline quantifies what the improvement is worth before you commit to chasing it.
Results at a glance
- Protected days of supply: 32.09 days (headline result)
- Unprotected days: 35.29 days
- Inventory: 3,000 pieces
- Daily usage: 85 pieces / day
Run it with your numbers
- Every input above is editable in the live Raw Material Buffer calculator, which recalculates instantly and can be shared with the inputs intact.
Last reviewed 2026-05-12.