Process Skids, Modular Equipment & Packaged Plants worked example
FAT Duration at 7.2% retest and contingency allowance: a worked example
This worked example runs the fat duration numbers for a tougher week than the baseline: 7.2% retest and contingency allowance instead of the typical 10%. FAT Duration estimates how many hours a Factory Acceptance Test on a process skid will actually take, from the number of test points and how fast your team works through them, plus a realistic allowance for retests.
The inputs for this scenario
- FAT test points to execute: 120 units (held at the documented default)
- Test point execution rate: 12 units / hr (held at the documented default)
- Retest and contingency allowance: 7.2 % (the input this scenario stresses; the baseline uses 10)
Working through the calculation
- The calculation starts from the formula this tool documents: Base FAT duration time = required work รท processing rate.
- Adjusted run time works out to 10.72 hr at these inputs, and this is the headline figure for the scenario.
- Base run time works out to 10 hr at these inputs.
- Allowance applied works out to 7.2 % at these inputs.
- Process rate works out to 12 pieces / min at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where retest and contingency allowance sits at 10% and the headline result is 11 hr, this scenario comes in 2.55% below the baseline at 10.72 hr.
- Use it when scheduling a witnessed FAT, booking client and inspector travel, or sequencing FAT against the skid ship date. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- Adjusted run time: 10.72 hr (headline result)
- Base run time: 10 hr
- Allowance applied: 7.2 %
- Process rate: 12 pieces / min
Run it with your numbers
- To rerun this with your own numbers, open the live FAT Duration calculator, set retest and contingency allowance to your actual value, and adjust the remaining inputs to match your operation.
Last reviewed 2026-05-12.