Pump, Compressor & Rotating Equipment Assembly worked example

Paint Booth Capacity at 65% booth uptime: a worked example in pump, compressor & rotating equipment assembly

Here is what the math looks like when conditions slip. We hold every other input steady and drop booth uptime to 65%, then walk the calculation through step by step. Paint booth capacity estimates how many good, coated pump or compressor assemblies a booth can actually deliver over a period, after uptime and coating yield losses are taken out of the gross count.

The inputs for this scenario

  • Assemblies coated per booth cycle: 4 units / cycle (held at the documented default)
  • Available booth cycles: 480 cycles (held at the documented default)
  • Booth uptime: 65 % (the input this scenario stresses; the baseline uses 90)
  • Coating first-pass yield: 97 % (held at the documented default)

Working through the calculation

  • The calculation starts from the formula this tool documents: Gross paint booth capacity capacity = units per cycle × available cycles.
  • Good output capacity works out to 1,211 units at these inputs, and this is the headline figure for the scenario.
  • Gross capacity works out to 1,920 units at these inputs.
  • Uptime loss works out to 672 units at these inputs.
  • Yield loss works out to 37.44 units at these inputs.

How this compares with the baseline

  • Against the tool's baseline example, where booth uptime sits at 90% and the headline result is 1,676 units, this scenario comes in 27.78% below the baseline at 1,211 units.
  • The practical read: the gap between this scenario and the baseline is entirely attributable to booth uptime, so recovering it is worth quantifying in dollars before considering equipment or staffing changes. It uses a single average units-per-cycle; mixed part sizes that load the booth differently will make one blended figure less accurate than modeling by part family.

Results at a glance

  • Good output capacity: 1,211 units (headline result)
  • Gross capacity: 1,920 units
  • Uptime loss: 672 units
  • Yield loss: 37.44 units

Run it with your numbers

  • To rerun this with your own numbers, open the live Paint Booth Capacity calculator, set booth uptime to your actual value, and adjust the remaining inputs to match your operation.