Refractories, Furnace Linings & Foundry Consumables worked example

Anchor Count at 99% crew and equipment uptime: a worked example

Push crew and equipment uptime up to 99% and the picture changes. This example computes every intermediate figure at that operating point. Use it when anchor count in refractories, furnace linings and foundry consumables is being asked to take on more work and you need to know if there is room.

The inputs for this scenario

  • Anchors welded per work cycle: 4 units / cycle (unchanged)
  • Work cycles available in the outage: 480 cycles (unchanged)
  • Crew and equipment uptime: 99 % (raised for this scenario; the documented default is 90)
  • First-pass weld yield: 97 % (unchanged)

Working through the calculation

  • Applying the documented formula (Gross anchor count capacity = units per cycle × available cycles) to the inputs above produces each figure below.
  • At this operating point the engine returns 1,844 units for good output capacity, the number this scenario is built around.
  • At this operating point the engine returns 1,920 units for gross capacity.
  • At this operating point the engine returns 19.2 units for uptime loss.
  • At this operating point the engine returns 57.02 units for yield loss.

How this compares with the baseline

  • Against the tool's baseline example, where crew and equipment uptime sits at 90% and the headline result is 1,676 units, this scenario comes in 10% above the baseline at 1,844 units.
  • Computes good anchor installation capacity as anchors per cycle times available cycles, then derated by crew uptime and first-pass weld yield. The value of this scenario is the size of the gap it exposes: that gap, priced out over a year, is the budget you can justify spending to close it.

Results at a glance

  • Good output capacity: 1,844 units (headline result)
  • Gross capacity: 1,920 units
  • Uptime loss: 19.2 units
  • Yield loss: 57.02 units