Sheet Metal Stamping & Press Lines worked example

Shift Output at 99% line efficiency: a worked example

What does the result look like when line efficiency reaches 99%? The full calculation is worked below with real intermediate numbers. Use it when shift output in sheet metal stamping and press lines is being committed and you need a throughput number you can defend.

The inputs for this scenario

  • Good stamped parts completed this shift: 1,200 units (unchanged)
  • Press runtime this shift: 8 hr (unchanged)
  • Line efficiency (OEE-style): 99 % (raised for this scenario; the documented default is 90)

Working through the calculation

  • Applying the documented formula (Raw shift output = completed output ÷ runtime) to the inputs above produces each figure below.
  • At this operating point the engine returns 149 units / hr for effective throughput, the number this scenario is built around.
  • At this operating point the engine returns 150 units / hr for raw throughput.
  • At this operating point the engine returns 99 % for efficiency.
  • At this operating point the engine returns 8 hr for runtime.

How this compares with the baseline

  • Against the tool's baseline example, where line efficiency sits at 90% and the headline result is 135 units / hr, this scenario comes in 10% above the baseline at 149 units / hr.
  • A figure at this level is achievable when line efficiency is genuinely sustained, not just peaked for a shift. It uses a single blended efficiency; it will not tell you whether a shortfall came from availability (downtime) versus performance (slow strokes) — those need a full OEE breakdown.

Results at a glance

  • Effective throughput: 149 units / hr (headline result)
  • Raw throughput: 150 units / hr
  • Efficiency: 99 %
  • Runtime: 8 hr

Run it with your numbers

  • Every input above is editable in the live Shift Output calculator, which recalculates instantly and can be shared with the inputs intact.