Field Install Hours with number of sign locations to install of 6 items: a worked example

Suppose number of sign locations to install falls to 6 items. This page works the full calculation at that level so you can see exactly which result moves and by how much. Estimate total field installation labor hours for Signage, Displays & Architectural Graphics from the number of items and the hours each takes.

The inputs for this scenario

  • Number of sign locations to install: 6 items (the input this scenario stresses; the baseline uses 12)
  • Install labor hours per sign location: 6 hr (held at the documented default)
  • Installers on the crew: 2 people (held at the documented default)

Working through the calculation

  • The calculation starts from the formula this tool documents: Total labor hours = work items × hours per item.
  • Total labor hours works out to 36 hr at these inputs, and this is the headline figure for the scenario.
  • Duration with crew works out to 18 hr at these inputs.
  • Work items works out to 6 items at these inputs.
  • Hours per item works out to 6 hr / item at these inputs.

How this compares with the baseline

  • Against the tool's baseline example, where number of sign locations to install sits at 12 items and the headline result is 72 hr, this scenario comes in 50% below the baseline at 36 hr.
  • It multiplies the number of sign locations by the labor hours each takes to get total labor hours, then divides by crew size to get elapsed on-site duration. When the numbers land here, the stressed input is the lever to work; the walkthrough above shows exactly how much each output recovers as it climbs back toward the baseline.

Results at a glance

  • Total labor hours: 36 hr (headline result)
  • Duration with crew: 18 hr
  • Work items: 6 items
  • Hours per item: 6 hr / item