Supply Chain & Procurement worked example
Supplier Payment Terms Impact at 92% fraction of terms change realized: a worked example
What does the result look like when fraction of terms change realized reaches 92%? The full calculation is worked below with real intermediate numbers. Use it when supplier payment terms impact in supply chain and procurement is being put through a supply chain and procurement weighted-cost review.
The inputs for this scenario
- Annual spend with the supplier: 100 units (unchanged)
- Cost of capital per dollar-year: 45 $ / unit (unchanged)
- Fraction of terms change realized: 92 % (raised for this scenario; the documented default is 80)
- One-time transition cost: 250 $ (unchanged)
Working through the calculation
- Applying the documented formula (Weighted cost = quantity × rate × capture factor + fixed adjustment) to the inputs above produces each figure below.
- At this operating point the engine returns 4,390 $ for total supplier payment terms impact cost, the number this scenario is built around.
- At this operating point the engine returns 43.9 $ / piece for supplier payment terms impact cost per unit.
- At this operating point the engine returns 4,140 $ for variable supplier payment terms impact cost.
- At this operating point the engine returns 250 $ for fixed supplier payment terms impact adder.
How this compares with the baseline
- Against the tool's baseline example, where fraction of terms change realized sits at 80% and the headline result is 3,850 $, this scenario comes in 14.03% above the baseline at 4,390 $.
- A figure at this level is achievable when fraction of terms change realized is genuinely sustained, not just peaked for a shift. It is a working-capital approximation, not a full NPV — it ignores the price increase suppliers often bake in for longer terms and the effect on supplier financial health, both of which can erase the paper gain.
Results at a glance
- Total supplier payment terms impact cost: 4,390 $ (headline result)
- Supplier payment terms impact cost per unit: 43.9 $ / piece
- Variable supplier payment terms impact cost: 4,140 $
- Fixed supplier payment terms impact adder: 250 $
Run it with your numbers
- Every input above is editable in the live Supplier Payment Terms Impact calculator, which recalculates instantly and can be shared with the inputs intact.
Last reviewed 2026-05-12.