Tooling, Fixtures, Dies & Mold Economics worked example
Spare Tooling Inventory with spare tooling daily usage of 3,000 units / day: a worked example
This scenario runs the spare tooling inventory calculation on the strong side: spare tooling daily usage of 3,000 units / day, with every other input held at its documented default. Use it when spare tooling inventory in tooling, fixtures, dies and mold economics is being sized for a buffer or safety stock review.
The inputs for this scenario
- Spare tooling daily usage: 3,000 units / day (raised for this scenario; the documented default is 1,200)
- Replenishment lead time: 85 days (unchanged)
- Safety stock multiplier: 1.1 units (unchanged)
Working through the calculation
- Applying the documented formula (Spare tooling inventory cycle stock = spare tooling inventory daily usage × spare tooling inventory lead time) to the inputs above produces each figure below.
- At this operating point the engine returns 32.09 days for protected days of supply, the number this scenario is built around.
- At this operating point the engine returns 35.29 days for unprotected days.
- At this operating point the engine returns 3,000 pieces for inventory.
- At this operating point the engine returns 85 pieces / day for daily usage.
How this compares with the baseline
- Against the tool's baseline example, where spare tooling daily usage sits at 1,200 units / day and the headline result is 12.83 days, this scenario comes in 150% above the baseline at 32.09 days.
- Use it when setting reorder points and quantities for perishable or spare tooling, sizing a new tool-crib stocking level, or checking whether current on-hand stock covers supplier lead time. Treat this as a target state: the delta against the baseline quantifies what the improvement is worth before you commit to chasing it.
Results at a glance
- Protected days of supply: 32.09 days (headline result)
- Unprotected days: 35.29 days
- Inventory: 3,000 pieces
- Daily usage: 85 pieces / day
Run it with your numbers
- Every input above is editable in the live Spare Tooling Inventory calculator, which recalculates instantly and can be shared with the inputs intact.
Last reviewed 2026-05-12.