Tunnel Boring & Heavy Civil Equipment worked example

Field Commissioning Hours at 12% setup, handling, and delay allowance: a worked example

Push setup, handling, and delay allowance up to 12% and the picture changes. This example computes every intermediate figure at that operating point. Use it when field commissioning hours in tunnel boring and heavy civil equipment is changing rate or allowance and you want to see the impact.

The inputs for this scenario

  • Field commissioning tasks or test points: 120 units (unchanged)
  • Commissioning completion rate: 12 units / min (unchanged)
  • Setup, handling, and delay allowance: 12 % (raised for this scenario; the documented default is 10)

Working through the calculation

  • Applying the documented formula (Base field commissioning hours time = field commissioning hours workload รท field commissioning hours completion rate) to the inputs above produces each figure below.
  • At this operating point the engine returns 11.2 hr for required field commissioning hours time, the number this scenario is built around.
  • At this operating point the engine returns 10 hr for base field commissioning hours time.
  • At this operating point the engine returns 12 % for field commissioning hours allowance applied.
  • At this operating point the engine returns 12 pieces / min for field commissioning hours completion rate.

How this compares with the baseline

  • Against the tool's baseline example, where setup, handling, and delay allowance sits at 10% and the headline result is 11 hr, this scenario comes in 1.82% above the baseline at 11.2 hr.
  • It divides the commissioning workload by the completion rate to get a base time, then inflates it by the setup and delay allowance to get the required time. The value of this scenario is the size of the gap it exposes: that gap, priced out over a year, is the budget you can justify spending to close it.

Results at a glance

  • Required field commissioning hours time: 11.2 hr (headline result)
  • Base field commissioning hours time: 10 hr
  • Field commissioning hours allowance applied: 12 %
  • Field commissioning hours completion rate: 12 pieces / min

Run it with your numbers

  • Every input above is editable in the live Field Commissioning Hours calculator, which recalculates instantly and can be shared with the inputs intact.

Last reviewed 2026-05-12.