Asphalt, Road Materials & Paving Products worked example

Asphalt Cost Per Ton at 110% cost share applied to this job: a worked example

What does the result look like when cost share applied to this job reaches 110%? The full calculation is worked below with real intermediate numbers. an estimator needs a defensible cost per ton for HMA, WMA, cold mix, patch mix, or a paving quote

The inputs for this scenario

  • Asphalt mix tonnage for the job: 1,250 tons (unchanged)
  • Variable asphalt cost per ton (mix + trucking): 82 $ / ton (unchanged)
  • Cost share applied to this job: 110 % (raised for this scenario; the documented default is 100)
  • Fixed mobilization and plant setup cost: 4,500 $ (unchanged)

Working through the calculation

  • Applying the documented formula (Variable asphalt cost = asphalt mix tonnage × variable asphalt cost × cost share applied to job) to the inputs above produces each figure below.
  • At this operating point the engine returns 117,250 $ for total asphalt job cost, the number this scenario is built around.
  • At this operating point the engine returns 93.8 $ / ton for cost per asphalt ton.
  • At this operating point the engine returns 112,750 $ for variable asphalt cost.
  • At this operating point the engine returns 4,500 $ for fixed paving or plant cost.

How this compares with the baseline

  • Against the tool's baseline example, where cost share applied to this job sits at 100% and the headline result is 107,000 $, this scenario comes in 9.58% above the baseline at 117,250 $.
  • A figure at this level is achievable when cost share applied to this job is genuinely sustained, not just peaked for a shift. It assumes one blended variable rate; if your mix grade, polymer content or haul distance changes mid-job, run separate calculations per segment because a single average will misstate cost on mixed-spec work.

Results at a glance

  • Total asphalt job cost: 117,250 $ (headline result)
  • Cost per asphalt ton: 93.8 $ / ton
  • Variable asphalt cost: 112,750 $
  • Fixed paving or plant cost: 4,500 $