Building Materials Manufacturing worked example
Cement Plant OEE at 99% performance: a worked example
This scenario runs the cement plant oee calculation on the strong side: 99% performance, with every other input held at its documented default. Use it to benchmark line effectiveness and target the biggest loss in Building Materials Manufacturing.
The inputs for this scenario
- Operating (run) time: 410 min (unchanged)
- Planned production time: 480 min (unchanged)
- Performance: 99 % (raised for this scenario; the documented default is 95)
- Quality (first-pass yield): 98 % (unchanged)
Working through the calculation
- Applying the documented formula (Availability = operating time ÷ planned production time) to the inputs above produces each figure below.
- At this operating point the engine returns 82.87 % for oee, the number this scenario is built around.
- At this operating point the engine returns 85.42 % for availability.
- At this operating point the engine returns 99 % for performance.
- At this operating point the engine returns 98 % for quality.
How this compares with the baseline
- Against the tool's baseline example, where performance sits at 95% and the headline result is 79.52 %, this scenario comes in 4.21% above the baseline at 82.87 %.
- Use it on any continuous cement asset — kiln, raw mill, cement mill, or packing line — when you have run time, planned time, and reasonable performance and quality estimates. Treat this as a target state: the delta against the baseline quantifies what the improvement is worth before you commit to chasing it.
Results at a glance
- OEE: 82.87 % (headline result)
- Availability: 85.42 %
- Performance: 99 %
- Quality: 98 %
Run it with your numbers
- Every input above is editable in the live Cement Plant OEE calculator, which recalculates instantly and can be shared with the inputs intact.
Last reviewed 2026-05-12.