S&OP, Demand Planning & Forecasting worked example
S&OP Meeting Load at 7.2% setup, discussion and delay allowance: a worked example
This worked example runs the s&op meeting load numbers for a tougher week than the baseline: 7.2% setup, discussion and delay allowance instead of the typical 10%. Estimate s&op meeting load for sandop, demand planning and forecasting using production-ready inputs so teams can plan labor hours, schedule the work, or check whether the job fits the available shift time.
The inputs for this scenario
- S&OP prep items to work through (agenda/exceptions): 120 units (held at the documented default)
- Items cleared per minute of working time: 12 units / min (held at the documented default)
- Setup, discussion and delay allowance: 7.2 % (the input this scenario stresses; the baseline uses 10)
Working through the calculation
- The calculation starts from the formula this tool documents: Base s&op meeting load time = s&op meeting load workload รท s&op meeting load completion rate.
- Required s&op meeting load time works out to 10.72 hr at these inputs, and this is the headline figure for the scenario.
- Base s&op meeting load time works out to 10 hr at these inputs.
- S&op meeting load allowance applied works out to 7.2 % at these inputs.
- S&op meeting load completion rate works out to 12 pieces / min at these inputs.
How this compares with the baseline
- Against the tool's baseline example, where setup, discussion and delay allowance sits at 10% and the headline result is 11 hr, this scenario comes in 2.55% below the baseline at 10.72 hr.
- Use it when scoping the effort for an S&OP cycle step - demand review prep, exception clearing, or reconciliation - so you can plan staffing and calendar time realistically. A result at this level usually justifies acting on the stressed input before touching anything else, because every other figure in the table is downstream of it.
Results at a glance
- Required s&op meeting load time: 10.72 hr (headline result)
- Base s&op meeting load time: 10 hr
- S&op meeting load allowance applied: 7.2 %
- S&op meeting load completion rate: 12 pieces / min
Run it with your numbers
- To rerun this with your own numbers, open the live S&OP Meeting Load calculator, set setup, discussion and delay allowance to your actual value, and adjust the remaining inputs to match your operation.
Last reviewed 2026-05-12.