Commercial Kitchen Equipment calculator

Production Ramp Planner Calculator

Plan how many units a production ramp delivers while the crew learns the new model. You need the first-unit build hours, a progress ratio, build hours per week, weeks in the ramp and the units needed.

What this calculator does

  • Units a new kitchen equipment model's ramp will build as the crew learns, from first-unit hours and a progress ratio, against the units needed.

Formula used

  • Learning exponent e = log2(progress ratio ÷ 100); the xth unit takes first-unit build hours × x^e (Wright's law)
  • Units built in the ramp = (build hours per week × weeks in the ramp × (1 + e) ÷ first-unit build hours)^(1 ÷ (1 + e)), rounded down
  • Build hours for the plan = first-unit build hours × units needed^(1 + e) ÷ (1 + e); weeks needed = that ÷ build hours per week
  • Hours on the last unit = first-unit build hours × units built^e; units over plan = units built − units needed

Inputs explained

  • First-Unit Build Hours: Hours the first unit of the new model takes to build.
  • Progress Ratio: Unit hours left each time cumulative output doubles; 85% means 15% faster.
  • Build Hours per Week: Direct build hours the crew works each week.
  • Weeks in the Ramp: Weeks from the first unit to the end of the ramp.
  • Units Needed by the End: Units the plan needs built by the end of the ramp.

How to use the result

  • Best suited to planning the launch of a new model, checking a ramp against a ship date, seeing what more build hours are worth.
  • Does not cover a design or crew change part way through, which can interrupt the learning.

Current U.S. benchmarks

  • Industrial natural gas averages $4.34 per Mcf (EIA, Aug 2026), down 2.9% from a year earlier, with industrial electricity at 9.64 cents per kWh. Process heating and refrigeration budgets track both.
  • Steel mill PPI stands at 399.65 (BLS, Oct 2026), up 32.9% from a year earlier. New factory orders are up 10.5% year over year (Census).

Common questions

  • What is the progress ratio? The share of unit hours left each time cumulative output doubles. At 85%, the second unit takes 85% of the first unit's hours.
  • What progress ratio should I use? Your own history from the last model launch. NASA quotes 75% to 85% for complex machine tools for new models.
  • Why is the unit count an approximation? It uses the smooth form of Wright's law for total hours, which slightly overstates them, so the count errs low.
  • Does this include downtime? No. Enter the build hours the crew actually works each week, after downtime and other work.

Last reviewed 2026-11-12.