Doors, Hardware & Access Control Manufacturing calculator

Custom Order Lead-Time Coverage Calculator

Find how many custom openings or hardware sets you need on hand and on order to ride out a replenishment lead time plus a schedule-change buffer. You need daily demand, lead time, buffer days and committed supply.

What this calculator does

  • Supply that custom door and hardware orders need across their replenishment lead time, and how much to release now.

Formula used

  • Lead-time demand = daily demand × replenishment lead time
  • Schedule-change buffer stock = daily demand × buffer days
  • Required lead-time coverage = lead-time demand + buffer stock
  • Days covered = openings or sets on hand and on order ÷ daily demand
  • To release now = the larger of 0 and required coverage − committed supply

Inputs explained

  • Daily Custom Opening or Hardware Demand: Average openings or sets released per day over recent weeks.
  • Custom Order Replenishment Lead Time: Days from releasing a custom order to having it available.
  • Schedule-Change Buffer: Extra days of demand held for late releases and change orders.
  • Openings or Sets on Hand and on Order: On hand plus on order, minus backorders, from your inventory report.

How to use the result

  • Best suited to timing the next custom frame or hardware release, sizing a buffer for a change-prone project.
  • One large project release can exceed several days of average demand; size the buffer to your largest typical release. Buffer days are your judgment; the page sets no service level and ignores demand variability.

Current U.S. benchmarks

  • U.S. housing starts run at 1,309k per year (Census, Oct 2026), up 2.8% from a year earlier, the demand driver for building products.
  • Steel mill PPI stands at 399.65 (BLS, Oct 2026), up 32.9% from a year earlier. New factory orders are up 10.5% year over year (Census).

Common questions

  • Why enter the buffer in days instead of a multiplier? Days of demand can be checked against a real late release or slipped delivery, while a multiplier hides that. A 1.1 multiplier on a 35-day lead time equals 3.5 days, the default here.
  • What counts as committed supply for custom openings? Count sets on hand plus custom orders released and not yet received, minus backorders you owe. That inventory position, not shelf stock alone, is what the reorder rule compares with the requirement.
  • How much does each extra day of lead time add? Each day adds one day of demand to the requirement. At 25 openings or sets per day, cutting the lead time from 35 to 30 days lowers required coverage by 125.
  • Should I count working days or calendar days? Use the basis your lead time is quoted in and match demand to it. If the factory quotes calendar days and you ship five days a week, 25 per working day becomes about 17.9 per calendar day.

Last reviewed 2026-10-28.