ERP & MRP Planning calculator
Labor Plan Requirement Calculator
Convert planned output and support work into person-hours. Enter the labor standard, setup and indirect hours, usable time per worker and assigned crew.
What this calculator does
- Calculate person-hour load and the minimum equivalent crew needed within available working hours.
Formula used
- Run hours = planned units × standard person-hours per unit
- Support hours = setup person-hours + indirect person-hours
- Required hours = run hours + support hours
- Worker equivalent = required hours ÷ hours per worker; minimum workers = ceiling(worker equivalent)
- Capacity gap = assigned workers × hours per worker − required hours
Inputs explained
- Planned Units: Required output covered by this resource plan.
- Standard Labor Hours per Unit: Standard person-hours per unit, excluding separate setup and indirect work.
- Setup Labor Hours: Total setup person-hours across all planned lots.
- Indirect Labor Hours: Additional support person-hours excluded from the unit standard.
- Available Hours per Worker: Net usable hours per resource in this planning period.
- Assigned Workers: Interchangeable workers assigned to this plan.
How to use the result
- Best suited to weekly crew planning, support workload budgeting.
- Does not build a skill matrix or shift roster.
Current U.S. benchmarks
- Average hourly earnings of production and nonsupervisory workers in U.S. manufacturing are $30.43 (BLS, Oct 2026), up 3.8% from a year earlier. Median machinist pay is $28.24/hr (OEWS 2025), with state medians on each state page. Manufacturers have 584k open positions nationally (BLS JOLTS).
- U.S. manufacturing runs at 77.1% of capacity (Federal Reserve, Oct 2026). New factory orders are up 10.5% year over year (Census).
Common questions
- Are labor hours the same as elapsed hours? No. Two people working for one hour consume two person-hours. Enter total labor content across the crew.
- Is the minimum crew a staffing recommendation? It is a workload lower bound. Skills, breaks, simultaneous work and shift coverage may require a larger crew.
- Why use 0.01-hour time precision? It makes the whole-worker ceiling reproducible at exact capacity boundaries. Enter every time to hundredths of an hour; unsupported fractions are rejected.
- Should standard labor already include indirect work? Exclude any support work entered separately here. If your standard already includes it, enter zero in the corresponding support field.
Last reviewed 2026-10-13.