ERP & MRP Planning calculator

Purchase Replenishment Cycle Time Calculator

Check the full path from a requisition to usable purchased inventory. Enter four sequential elapsed durations and the maximum cycle allowed by your material plan.

What this calculator does

  • Add the sequential purchase-replenishment stages and compare the elapsed path with your required lead-time limit.

Formula used

  • Replenishment cycle = approval + supplier processing + transit + receiving
  • Internal processing = approval + receiving
  • Supplier share = supplier processing ÷ replenishment cycle × 100
  • Cycle headroom = allowed cycle − replenishment cycle

Inputs explained

  • Requisition and Approval Time: Elapsed time from requisition entry to released purchase order.
  • Supplier Confirmation and Production: Elapsed time from released order to supplier dispatch readiness.
  • Transit and Customs Time: Elapsed transport and border time before arrival at receiving.
  • Receiving and Inspection Release: Elapsed time from arrival until inventory becomes usable.
  • Allowed Replenishment Cycle: Maximum complete-path duration allowed by the material plan.

How to use the result

  • Best suited to Purchased-Part Lead-Time audit, replenishment delay review.
  • This duration does not calculate calendar dates, holidays or route alternatives. Purchase-order issue time alone ends when the order reaches the supplier.

Current U.S. benchmarks

  • Average hourly earnings of production and nonsupervisory workers in U.S. manufacturing are $30.43 (BLS, Oct 2026), up 3.8% from a year earlier. Median machinist pay is $28.24/hr (OEWS 2025), with state medians on each state page. Manufacturers have 584k open positions nationally (BLS JOLTS).
  • U.S. manufacturing runs at 76.1% of capacity (Federal Reserve, Oct 2026). New factory orders are up 10.5% year over year (Census).

Common questions

  • Does this measure only purchase-order approval? No. It includes supplier production, transit and receiving release after approval. The visible name distinguishes the complete replenishment path from internal order issue time.
  • Can I add working days to calendar days? No. Convert every stage to the same elapsed-day basis first. Supplier and receiving calendars can otherwise understate the full time to usable stock.
  • What if two stages overlap? Do not add their full overlapping durations. Enter only sequential elapsed segments or use a dated network schedule for parallel activities.
  • Why is supplier share blank for a zero cycle? There is no meaningful percentage of a zero-duration total. Enter the observed stage times before comparing their shares.

Last reviewed 2026-10-13.