ERP & MRP Planning calculator
Schedule Delay Exposure Calculator
Test a specific disruption against the remaining deadline slack. Enter the remaining duration, time until due, added delay and confirmed recovery of that delay.
What this calculator does
- Estimate how many days late a stated disruption would leave the committed production milestone.
Formula used
- Baseline slack = time until due − remaining duration
- Net delay = disruption delay − recovered delay
- Completion offset = remaining duration + net delay
- Remaining slack = time until due − completion offset
- Projected lateness = max(0, −remaining slack)
Inputs explained
- Remaining Planned Duration: Elapsed calendar duration of the remaining completion path.
- Time Until Due: Calendar days from the reference time to the committed deadline.
- Additional Disruption Delay: Extra elapsed days added by the specific disruption scenario.
- Confirmed Delay Recovery: Disruption days removed by a confirmed recovery action.
How to use the result
- Best suited to supplier delay scenarios, recovery plan reviews.
- Multiple paths, correlated events and uncertain durations need a network schedule risk analysis.
Current U.S. benchmarks
- Average hourly earnings of production and nonsupervisory workers in U.S. manufacturing are $30.43 (BLS, Oct 2026), up 3.8% from a year earlier. Median machinist pay is $28.24/hr (OEWS 2025), with state medians on each state page. Manufacturers have 584k open positions nationally (BLS JOLTS).
- U.S. manufacturing runs at 76.1% of capacity (Federal Reserve, Oct 2026). New factory orders are up 10.5% year over year (Census).
Common questions
- Is this a risk probability? No. It shows the finish consequence of one entered scenario without assigning any event likelihood.
- Can time until due be negative? Yes. A negative value records how far the committed deadline has already passed.
- Why is recovery limited to the disruption? This input represents removal of the added delay. Model improvements to the baseline process by revising the remaining planned duration separately.
- What if another path controls completion? Use the duration of the path that determines the milestone after the disruption. A full network schedule is needed when that path changes.
Last reviewed 2026-10-13.