ERP & MRP Planning calculator

Schedule Delay Exposure Calculator

Test a specific disruption against the remaining deadline slack. Enter the remaining duration, time until due, added delay and confirmed recovery of that delay.

What this calculator does

  • Estimate how many days late a stated disruption would leave the committed production milestone.

Formula used

  • Baseline slack = time until due − remaining duration
  • Net delay = disruption delay − recovered delay
  • Completion offset = remaining duration + net delay
  • Remaining slack = time until due − completion offset
  • Projected lateness = max(0, −remaining slack)

Inputs explained

  • Remaining Planned Duration: Elapsed calendar duration of the remaining completion path.
  • Time Until Due: Calendar days from the reference time to the committed deadline.
  • Additional Disruption Delay: Extra elapsed days added by the specific disruption scenario.
  • Confirmed Delay Recovery: Disruption days removed by a confirmed recovery action.

How to use the result

  • Best suited to supplier delay scenarios, recovery plan reviews.
  • Multiple paths, correlated events and uncertain durations need a network schedule risk analysis.

Current U.S. benchmarks

  • Average hourly earnings of production and nonsupervisory workers in U.S. manufacturing are $30.43 (BLS, Oct 2026), up 3.8% from a year earlier. Median machinist pay is $28.24/hr (OEWS 2025), with state medians on each state page. Manufacturers have 584k open positions nationally (BLS JOLTS).
  • U.S. manufacturing runs at 76.1% of capacity (Federal Reserve, Oct 2026). New factory orders are up 10.5% year over year (Census).

Common questions

  • Is this a risk probability? No. It shows the finish consequence of one entered scenario without assigning any event likelihood.
  • Can time until due be negative? Yes. A negative value records how far the committed deadline has already passed.
  • Why is recovery limited to the disruption? This input represents removal of the added delay. Model improvements to the baseline process by revising the remaining planned duration separately.
  • What if another path controls completion? Use the duration of the path that determines the milestone after the disruption. A full network schedule is needed when that path changes.

Last reviewed 2026-10-13.