Industrial Equipment, Machinery & Capital Goods calculator
Commissioning Delay Cost Calculator
Find what a commissioning delay costs you. You need the delay days, the daily site burn, the share of the delay you cannot bill to the customer and the penalty and recovery cost.
What this calculator does
- Cost of a commissioning overrun from the delay days, the daily site burn, the share you cannot recover and fixed penalty and recovery cost.
Formula used
- Variable delay cost ($) = commissioning delay days × site burn cost per delay day × unrecoverable exposure ÷ 100
- Total commissioning delay cost ($) = variable delay cost + fixed penalty and recovery cost
- All-in cost per delay day = total commissioning delay cost ÷ commissioning delay days
Inputs explained
- Commissioning Delay Days: Days commissioning ran past the plan.
- Site Burn Cost per Delay Day: Crew, lodging and equipment cost per day on site.
- Unrecoverable Delay Exposure: Share of the delay you cannot bill to the customer.
- Fixed Penalty and Recovery Cost: Liquidated damages and recovery actions, charged once.
How to use the result
- Best suited to settling who pays for an overrun, sizing the delay contingency in a fixed-price quote.
- Does not model the cost of the next project slipping. Ignores customer-caused delay you can bill.
Current U.S. benchmarks
- The U.S. prime lending rate is 7.00% (Federal Reserve via FRED, Nov 9, 2026). Payback and financing math should start from today's rate, not a remembered one.
- Steel mill PPI stands at 399.65 (BLS, Oct 2026), up 32.9% from a year earlier. New factory orders are up 10.5% year over year (Census).
- The U.S. has 21,668 machinery manufacturing establishments employing about 1,086,146 workers (Census County Business Patterns, 2023).
Common questions
- What is the site burn cost per day? Crew wages with burden, lodging and per diems, rented equipment and any idle freight, for one day on site.
- How do I set the unrecoverable exposure? From the contract and the cause: delay you caused is 100% unrecoverable, customer-caused waiting with a signed change order might be 0%.
- What belongs in penalty and recovery cost? Liquidated damages triggered by the delay, overtime to catch up and any extra trip needed to finish.
- How do I use the all-in day rate? It is the cost of each further day of slip, which tells you how much to spend on overtime or a second crew to finish sooner.
Last reviewed 2026-10-29.