Find whether the controls work for a machine fits its planned hours. You need the controls tasks, the completion rate per hour, the debug and field support allowance and the planned hours.
What this calculator does
- Controls engineering hours a machine needs from its tasks, the completion rate and the debug and field support allowance, against the hours the plan allows.
Formula used
- Base controls engineering time (hr) = controls tasks ÷ controls task completion rate
- Required controls engineering load (hr) = base controls engineering time × (1 + debug and field support allowance ÷ 100)
- Plan hours left = controls hours planned − required hours; load (%) = required ÷ planned × 100
Inputs explained
- Controls Tasks: Programming, drawing and checkout tasks for the controls.
- Controls Task Completion Rate: Tasks one controls engineer completes per hour.
- Debug and Field Support Allowance: Extra time for debugging and supporting the field.
- Controls Hours Planned: Hours the project plan allows for controls.
How to use the result
- Best suited to estimating controls on a quote, loading the controls group across projects.
- Does not model waiting for the panel build. Ignores reuse of standard code blocks.
Current U.S. benchmarks
- The U.S. prime lending rate is 7.00% (Federal Reserve via FRED, Nov 9, 2026). Payback and financing math should start from today's rate, not a remembered one.
- Steel mill PPI stands at 399.65 (BLS, Oct 2026), up 32.9% from a year earlier. New factory orders are up 10.5% year over year (Census).
- The U.S. has 21,668 machinery manufacturing establishments employing about 1,086,146 workers (Census County Business Patterns, 2023).
Common questions
- What is a controls task? A program module, a drawing sheet, a screen, a network setup or a checkout step. Count them from the last machine's task list.
- How do I measure the completion rate? Tasks completed divided by controls hours booked on the last comparable machine, excluding debug.
- What is in the debug and field support allowance? Debugging on the machine, FAT support, commissioning support and remote support after startup.
- What if the load exceeds 100%? Add a controls engineer, reuse more standard code or move debug earlier by simulating before the machine is ready.