Planning calculator
Reorder Point Calculator
Set the trigger that releases a purchase or work order, and check it against stock on hand plus open orders before you release another. You need daily demand, lead time, safety stock, on-hand stock and open orders.
What this calculator does
- The stock level that triggers a replenishment order, and whether your inventory position says order now.
Formula used
- Lead-time demand = average daily demand × lead time; reorder point = lead-time demand + safety stock
- Inventory position = on-hand inventory + open order quantity
- Position above reorder point = inventory position − reorder point (negative means order now)
- Days until reorder = MAX(position above reorder point, 0) ÷ average daily demand
- On-hand days of cover = on-hand inventory ÷ average daily demand, compared with lead time
Inputs explained
- Average Daily Demand: Mean daily usage over a recent, representative period.
- Lead Time: Days from placing the order to usable stock, including inspection.
- Safety Stock: Buffer held for demand and lead-time variation.
- On-Hand Inventory: Usable units on hand, less stock already allocated or backordered.
- Open Order Quantity: Units on firm purchase or work orders not yet received.
How to use the result
- Best suited to loading MRP reorder points after a demand refresh, daily buyer review of items near their trigger.
- With weekly or monthly review, add the review period to lead time or the trigger fires late. Takes safety stock as given; size it for your service target with the safety stock calculator.
Current U.S. benchmarks
- U.S. manufacturing runs at 75.7% of capacity (Federal Reserve, Aug 2026). New factory orders are up 8.5% year over year (Census).
Common questions
- Should I compare on-hand or inventory position with the reorder point? Inventory position: on-hand plus open orders, less backorders. Comparing on-hand alone fires a second order while the first is still in transit, so both arrive and stock overshoots.
- What if on-hand stock runs out before a new order could arrive? Then ordering now is not enough. At 360 a day, 2,100 units on hand last 5.8 days against a 9-day lead time: expedite, split the delivery or pull an open order in.
- How does a longer lead time change the reorder point? It adds one day of demand for each extra day. Stretching lead time from 9 to 15 days at 145 a day lifts the reorder point from 1,725 to 2,595 units, before any extra safety stock.
- Should demand and lead time be in working or calendar days? Either, as long as both use the same days. If you consume five days a week and the supplier quotes calendar days, convert lead time to working days first, or the reorder point runs high.
Related guides
Last reviewed 2026-10-01.