Manufacturing Project Portfolio & Capex calculator

Project Delay Cost Calculator

Quantify one schedule-slip scenario without treating contingent penalties as certain. Enter its duration, weekly cost, probability, contingent fixed costs, committed recovery spending and approved allowance.

What this calculator does

  • Estimate expected schedule-slip cost by weighting all delay-contingent costs and separately adding committed recovery spending.

Formula used

  • Conditional delay cost = delay weeks × weekly delay cost + fixed costs if delay occurs
  • Expected delay cost = conditional delay cost × delay probability / 100
  • Expected total = expected delay cost + committed recovery spending
  • Allowance remaining = approved delay allowance − expected total

Inputs explained

  • Schedule Slip: Use the modeled delay duration from the schedule risk review.
  • Incremental Weekly Delay Cost: Use added weekly costs caused solely by the schedule slip.
  • Delay Occurrence Probability: Use the documented chance that this delay scenario occurs.
  • Fixed Cost If Delay Occurs: Use penalties and remobilization payable only when the delay occurs.
  • Committed Recovery Spending: Use spending payable whether or not the delay occurs.
  • Approved Delay Allowance: Use the approved allowance for delay risk and recovery spending.

How to use the result

  • Best suited to equipment delivery slip, line commissioning recovery.
  • Expected cost is not the cash needed if the delay actually occurs. Multiple interacting scenarios, deferred benefits and discounting require a broader analysis.

Common questions

  • Should penalties be multiplied by the delay probability? Yes, if payable only when that delay occurs. Costs already committed regardless of the outcome belong in committed recovery spending.
  • What if the delay has already happened? Enter a one-hundred-percent probability and the expected remaining duration. Use remaining incremental costs and exclude sunk spending.
  • Is expected cost the required cash reserve? No. The realized cash exposure can be the conditional delay cost plus committed spending. Expected cost is a probability-weighted planning amount.
  • Does a zero-week delay still incur penalties? No. This model treats zero weeks as no delay event and removes delay-contingent fixed costs. Unconditional obligations remain in committed recovery spending.

Related guides

Last reviewed 2026-10-14.