Manufacturing Project Portfolio & Capex calculator
Project Delay Cost Calculator
Quantify one schedule-slip scenario without treating contingent penalties as certain. Enter its duration, weekly cost, probability, contingent fixed costs, committed recovery spending and approved allowance.
What this calculator does
- Estimate expected schedule-slip cost by weighting all delay-contingent costs and separately adding committed recovery spending.
Formula used
- Conditional delay cost = delay weeks × weekly delay cost + fixed costs if delay occurs
- Expected delay cost = conditional delay cost × delay probability / 100
- Expected total = expected delay cost + committed recovery spending
- Allowance remaining = approved delay allowance − expected total
Inputs explained
- Schedule Slip: Use the modeled delay duration from the schedule risk review.
- Incremental Weekly Delay Cost: Use added weekly costs caused solely by the schedule slip.
- Delay Occurrence Probability: Use the documented chance that this delay scenario occurs.
- Fixed Cost If Delay Occurs: Use penalties and remobilization payable only when the delay occurs.
- Committed Recovery Spending: Use spending payable whether or not the delay occurs.
- Approved Delay Allowance: Use the approved allowance for delay risk and recovery spending.
How to use the result
- Best suited to equipment delivery slip, line commissioning recovery.
- Expected cost is not the cash needed if the delay actually occurs. Multiple interacting scenarios, deferred benefits and discounting require a broader analysis.
Common questions
- Should penalties be multiplied by the delay probability? Yes, if payable only when that delay occurs. Costs already committed regardless of the outcome belong in committed recovery spending.
- What if the delay has already happened? Enter a one-hundred-percent probability and the expected remaining duration. Use remaining incremental costs and exclude sunk spending.
- Is expected cost the required cash reserve? No. The realized cash exposure can be the conditional delay cost plus committed spending. Expected cost is a probability-weighted planning amount.
- Does a zero-week delay still incur penalties? No. This model treats zero weeks as no delay event and removes delay-contingent fixed costs. Unconditional obligations remain in committed recovery spending.
Related guides
Last reviewed 2026-10-14.