Mining Vehicle & Underground Equipment calculator

Commissioning Load Calculator

Commissioning Load estimates the electricity a mining machine draws while it is run up, exercised, and signed off at end-of-line commissioning, and what that energy costs per machine. Test and commissioning engineers for haul trucks, battery-electric loaders, and underground utility vehicles use it because commissioning runs power packs, hydraulics, traction motors, and HVAC simultaneously for hours, and on battery-electric fleets that energy is a direct charging cost. Plant cost accountants fold the per-unit number into the cost of goods, while facilities teams use the connected-load figure to size feeders and demand charges. It converts a kW rating and a run time into kWh, dollars, and a clean per-machine figure.

What this calculator does

  • Estimate commissioning load for mining vehicle and underground equipment using production-ready inputs so teams can budget energy cost, compare equipment settings, or include electricity in the quote.
  • Use it when commissioning load in mining vehicle and underground equipment is being quoted and energy is a real chunk of the mining vehicle and underground equipment cost stack.
  • It computes commissioning energy in kWh, the total energy cost, the energy cost per machine, and the hourly cost from connected load, run time, rate, and units.

Formula used

  • Total commissioning load energy cost = commissioning load connected load × commissioning load runtime × blended electricity rate
  • Energy cost per kWh = total energy cost ÷ units processed during runtime

Inputs explained

  • Connected electrical load during commissioning:
  • Commissioning run time:
  • Blended electricity rate:
  • Machines commissioned during the run:

How to use the result

  • Use it when costing a commissioning procedure, sizing electrical supply for a test bay, or comparing the energy burden of a long burn-in against a shorter sequence.
  • Connected load is treated as a constant draw, but real commissioning ramps between idle and full load, so this is an upper-bound estimate unless you enter an average load.

Current U.S. benchmarks

  • As of Apr 2026, industrial electricity averages 8.7 cents per kWh across the U.S. (EIA), up 5.5% from a year earlier. State averages range widely, so plants should confirm against their own tariff.
  • U.S. light vehicles sell at a 16.9 million annual rate (BEA, Jun 2026), up 4.1% from a year earlier, the volume signal for automotive supply chains.
  • Steel mill PPI stands at 348.53 (BLS, May 2026), up 6.7% from a year earlier. New factory orders are up 2.3% year over year (Census).
  • The U.S. has 11,691 transportation equipment establishments employing about 1,682,910 workers (Census County Business Patterns, 2023).

Common questions

  • How do you calculate commissioning energy and cost? Multiply connected load by run time for kWh, then multiply by the electricity rate for cost. With 12 kW for 8 hours at $0.12/kWh, that is 96 kWh costing $11.52, or about $1.44 per hour.
  • What is the energy cost per machine during commissioning? Divide total energy cost by machines commissioned in the run. In the example, $11.52 across 1000 units works out to roughly $0.0115 per machine, since the run is shared across many units rather than one.
  • Should I use peak or average load for the connected-load input? Use average load if you have it, because commissioning cycles between idle and full draw. Using peak connected load gives a conservative upper-bound energy figure, which is fine for sizing feeders but overstates the per-unit cost.
  • Does this include charging losses for battery-electric machines? No. The calculator measures the energy the machine consumes during commissioning. For battery-electric loaders you should add charger and rectifier losses, typically 5 to 15 percent, on top of the computed kWh.
  • How do I cut commissioning energy cost? Shorten the run time, reduce simultaneous full-load operation, or commission during off-peak rate windows. Halving the 8-hour run to 4 hours would cut the example from 96 kWh and $11.52 to 48 kWh and $5.76.

Last reviewed 2026-05-12.