Electronics Repair, Refurbishment & Depot Operations calculator
RMA Queue Lead Time Calculator
Find how long a returned unit takes to come back, and whether that meets the target. You need the units in the queue, units completed a day, admin and hold days and the target.
What this calculator does
- Days an RMA takes from receipt to shipment from the queue, the daily completion rate and hold days, against the turnaround target.
Formula used
- Days in the bench queue = RMA units in the queue ÷ units completed per day (Little's law)
- RMA turnaround = admin and hold days + days in the bench queue
- Days over target = RMA turnaround − turnaround target
- Queue the target allows = units completed per day × (turnaround target − admin and hold days), or 0 when holds use up the target
Inputs explained
- RMA Units in the Queue: Units waiting for or on the bench, from the RMA log.
- Units Completed per Day: Average repairs shipped per working day over recent weeks.
- Admin and Hold Days: Days an RMA waits for approval, parts or a customer reply.
- Turnaround Target: Days the service agreement allows from receipt to shipment.
How to use the result
- Best suited to committing to a turnaround in a service agreement, sizing a backlog after a return surge, deciding whether to add a shift.
- Gives the average turnaround; units stuck waiting for parts can take far longer.
Current U.S. benchmarks
- The producer price index for primary nonferrous metals (a broad metals benchmark, not copper alone) stands at 589.63 (BLS, Oct 2026), up 42.7% from a year earlier. Quotes priced off last quarter's material cost miss this move.
- U.S. manufacturing runs at 76.1% of capacity (Federal Reserve, Oct 2026). New factory orders are up 10.5% year over year (Census).
- The U.S. has 11,261 computer and electronic products establishments employing about 815,443 workers (Census County Business Patterns, 2023).
Common questions
- Why divide the queue by completions per day? By Little's law, in a steady system the average number waiting equals the throughput times the average wait. So the bench queue in days is units waiting ÷ units completed a day.
- What belongs in admin and hold days? Time an RMA spends waiting for a repair approval, a quote, parts or a customer reply, outside the bench queue.
- How short must the queue be to meet the target? Completions a day times the target less hold days. At these defaults 60 a day over 8 days allows a 480-unit queue.
- What do the defaults show? 360 units in the queue at 60 completed a day wait 6 days; with 2 hold days the turnaround is 8 days against a 10-day target.