Permit Renewal Workload Calculator
Find out when a permit renewal has to start so the application goes in on time. You need the task count, hours per task, staff hours a week, weeks to expiry and the filing lead time.
What this calculator does
- Hours a permit renewal takes and the latest week to start it, working back from the expiry date and the filing lead time.
Formula used
- Permit renewal workload = renewal tasks × hours per task
- Weeks of work at this staffing = permit renewal workload ÷ staff hours per week
- Weeks until the application is due = weeks until the permit expires − filing lead time before expiry ÷ 7
- Weeks to spare before work must start = weeks until the application is due − weeks of work at this staffing
Inputs explained
- Renewal Tasks: Tasks in your renewal plan: sampling, forms, maps, reviews.
- Hours per Task: Average hours per task, from the last renewal or estimates.
- Staff Hours per Week: Hours a week your team can give the renewal.
- Weeks Until the Permit Expires: Weeks from today to the expiration date on the permit.
- Filing Lead Time Before Expiry: Days before expiry the application is due: 180 for NPDES.
How to use the result
- Best suited to planning an NPDES permit renewal, scheduling a title v renewal application, budgeting consultant hours for a renewal.
- Sampling that must happen in a season, or lab turnaround, can set a start date earlier than the hours alone suggest.
Common questions
- When is an NPDES renewal application due? 180 days before the existing permit expires, under 40 CFR 122.21(d), unless the permitting authority has granted a later date. It can never be later than the expiration date.
- When is a Title V renewal application due? At least 6 months before the permit expires, under 40 CFR 70.5, or a longer time the permitting authority approves. Enter 183 days, or your permit's own figure.
- What tasks belong in a renewal? Everything the application needs: effluent or emissions sampling, lab analysis, forms, site maps, process changes since the last permit and internal reviews. Count each as one task with its own hours.
- What if the weeks to spare are negative? The work cannot finish by the due date at current staffing. Add staff hours or a consultant now, and talk to the permitting authority before the due date, not after.
Last reviewed 2026-11-12.