Machine Vision & Industrial Inspection AI calculator
Inspection Automation Payback Calculator
Compare an inspection project with your maximum acceptable payback. Use the installed quote, steady annual savings, operating costs and months until savings start.
What this calculator does
- Find when inspection automation recovers its installed cost after commissioning.
Formula used
- Net annual savings = annual gross savings − annual operating cost
- Positive-investment payback = commissioning months ÷ 12 + installed investment ÷ positive net annual savings
- Payback target headroom = maximum payback − elapsed payback
- Operating savings payback = installed investment ÷ positive net annual savings
Inputs explained
- Installed Investment: Turnkey quote including installation and acceptance testing.
- Annual Gross Savings: Measured annual inspection costs the project will avoid.
- Annual Operating Cost: Annual maintenance, software, utilities and remaining support.
- Commissioning Delay: Months from spending until steady savings begin.
- Maximum Payback: Your approved maximum time to recover the investment.
How to use the result
- Best suited to automation capital request, commissioning schedule comparison.
- No discounting, tax, financing or residual value is included. Any commissioning expenses must already be included in installed investment.
Common questions
- Does payback start at installation or production acceptance? It starts when the investment is spent. The entered commissioning delay is added before steady operating savings recover the installed cost.
- What if operating cost exceeds savings? Payback is blank because there is no positive cash recovery. Negative annual savings remain visible and must be addressed before the financial case works.
- Can partial savings during commissioning be included? This model assumes none. Use an equivalent delay only if supported by your expected cash-flow schedule; use a period-by-period model for irregular savings.
- Does meeting the target prove the project is profitable? No. It only meets your simple recovery-time requirement. Service life, discounting, risk and benefits after payback need separate review.
Last reviewed 2026-10-23.