Office, School & Institutional Products calculator

Metal Frame Welding Time Calculator

When you schedule a batch of desk, chair or locker frames, find the welder hours it takes and whether the booth hours cover it. You need weld length per frame, travel speed, operator factor and fixture time.

What this calculator does

  • Welder hours for a batch of metal frames from weld length, travel speed, operator factor and fixture time.

Formula used

  • Arc-on time per frame (min) = weld length per frame ÷ travel speed
  • Welding time per frame (min) = arc-on time ÷ (operator factor ÷ 100) + fixture load and unload time
  • Batch welding time (hr) = frames × welding time per frame ÷ 60
  • Frames per welder hour = 60 ÷ welding time per frame
  • Welder hours used = batch welding time ÷ welder hours available × 100; spare = available − batch welding time

Inputs explained

  • Frames in the Batch: Frames on the work order for this welding batch.
  • Weld Length per Frame: Total of every weld length on the frame drawing.
  • Travel Speed: Torch travel speed from your welding procedure.
  • Operator Factor: Arc-on share of welding time, from a time study or weld monitor.
  • Fixture Load and Unload Time: Loading, tacking, clamping and unloading one frame.
  • Welder Hours Available: Booth hours scheduled for this batch across all welders.

How to use the result

  • Best suited to scheduling a desk frame batch in one booth, comparing manual booths with a robot cell.
  • Holds operator factor constant, though faster travel can lower it, so speed gains may be overstated. Excludes post-weld grinding, inspection and repair.

Common questions

  • What operator factor should I use for manual MIG welding of frames? Use your own time study or weld monitor data first. TWI lists 30 to 45% for manual gas metal arc welding and 80 to 90% mechanized, excluding setup and assembly time. TWI's lost time includes removal from the fixture, so with its figures leave unloading out of fixture time.
  • Why is fixture time entered separately from the operator factor? Because TWI's operating factor figures leave out setup and assembly time. Loading, tacking and unloading happen once per frame whatever the weld length, so they are added per frame instead of scaling with arc time.
  • How do I total the weld length on a tube frame? Add every weld on the drawing. A fully welded end of 1 by 2 inch tube is 6 inches around. Stitch welds count only their welded length, and a multipass weld counts once per pass.
  • Can I use this for a robotic welding cell? Yes. Enter the cell's measured arc-on share as the operator factor. If the robot welds at one station while you load the other, enter only the load time that stops the arc.

Last reviewed 2026-10-28.