Surgical Robotics Manufacturing calculator

Final System Burn-In Calculator

Find how long a batch of finished surgical systems will occupy burn-in, including connection, handling and log review. You need the system count, the bay throughput, the allowance and the hours scheduled.

What this calculator does

  • Station hours a batch of finished systems needs for burn-in, with connection and log review time, against the hours scheduled.

Formula used

  • Base burn-in hours = systems queued for burn-in ÷ systems through burn-in per hour
  • Required burn-in hours = base burn-in hours × (1 + allowance ÷ 100)
  • Burn-in hours left = burn-in hours scheduled − required hours; load (%) = required ÷ scheduled × 100

Inputs explained

  • Systems Queued for Burn-In: Complete systems waiting for burn-in.
  • Systems Through Burn-In per Hour: Systems the bays complete per hour of station time.
  • Setup, Handling and Delay Allowance: Extra time for connection, handling and log review.
  • Burn-In Hours Scheduled: Station hours scheduled for the batch.

How to use the result

  • Best suited to scheduling burn-in for a monthly build, sizing bays for a longer soak.
  • Does not model systems that fail burn-in and repeat it. Ignores power or cooling limits on bays.

Current U.S. benchmarks

  • U.S. manufacturing runs at 76.1% of capacity with new factory orders at $677B per month (Federal Reserve and Census, Sep 2026).
  • Global copper trades at $14,473 per tonne (IMF via FRED, Sep 2026), up 44.8% in a year, and U.S. industrial electricity averages 9.64 cents per kWh. Both feed electrified-hardware unit economics.
  • The U.S. has 8,825 medical equipment and supplies establishments employing about 308,388 workers (Census County Business Patterns, 2023).

Common questions

  • What is burn-in? Running finished systems under power and exercise before shipment to catch the components that fail early in life.
  • How do I set the throughput? Divide systems completed by station hours over a past batch. Twenty bays on a 48-hour soak complete about 0.42 systems an hour.
  • What goes into the allowance? Connecting and disconnecting systems, moving them in and out of bays, and reviewing the burn-in logs.
  • What if the required hours exceed the schedule? The calculator warns and shows the overrun. Add bays, shorten the queue or start burn-in earlier in the build.