PLM, BOM & Digital Thread calculator

Drawing Release Backlog Calculator

Find how long it will take to clear a backlog of drawings awaiting release. You need the drawing count, the release rate, the allowance and the checker hours scheduled.

What this calculator does

  • Checker hours a backlog of drawings needs to release, with checking and sign-off time, against the hours scheduled.

Formula used

  • Base release hours = drawings awaiting release ÷ drawings released per hour
  • Required release hours = base release hours × (1 + allowance ÷ 100)
  • Scheduled hours left = checker hours scheduled − required hours; load (%) = required ÷ scheduled × 100

Inputs explained

  • Drawings Awaiting Release: Drawings checked in but not yet released.
  • Drawings Released per Hour: Drawings one checker releases per hour, from the log.
  • Check, Sign-Off and Distribution Allowance: Extra time for checking, sign-off and distribution.
  • Checker Hours Scheduled: Hours scheduled to clear the backlog.

How to use the result

  • Best suited to clearing a backlog before a build starts, weekly drawing office load check.
  • Does not model drawings returned for correction. Ignores drawing complexity.

Common questions

  • What is a drawing awaiting release? A drawing finished by the designer and checked in, waiting for checking, approval signatures and release to the system of record.
  • How do I set the release rate? Divide drawings released by checker hours over a past backlog. The 5 per hour default is an example only.
  • What goes into the allowance? Detailed checking, collecting sign-offs and distributing the released drawing to the shop and suppliers.
  • What if the required hours exceed the schedule? The calculator warns and shows the overrun. Add a checker, release in build order or move the start date.