Surgical Robotics Manufacturing calculator

Spare Parts Buffer Calculator

Find how many spare parts you must hold to cover the supplier's lead time and a safety margin, and whether today's stock does. You need daily consumption, lead time, safety days and parts on hand.

What this calculator does

  • Spare parts stock needed to cover supplier lead time plus safety days, compared with the parts on hand.

Formula used

  • Lead-time demand = parts consumed per day × supplier replenishment lead time
  • Safety stock = parts consumed per day × safety stock days
  • Required stock = lead-time demand + safety stock
  • Stock above requirement = parts on hand − required stock; days of supply = parts on hand ÷ parts consumed per day

Inputs explained

  • Parts Consumed per Day: Service and consumable parts used per day across the fleet.
  • Supplier Replenishment Lead Time: Days from order to parts on the shelf.
  • Safety Stock Days: Days of demand held against demand and lead time variability.
  • Parts on Hand: Parts in stock and available today.

How to use the result

  • Best suited to setting reorder points for service parts, checking stock before a fleet expansion.
  • Does not compute an order quantity. Ignores parts already on order.

Current U.S. benchmarks

  • U.S. manufacturing runs at 76.1% of capacity with new factory orders at $677B per month (Federal Reserve and Census, Sep 2026).
  • Global copper trades at $14,473 per tonne (IMF via FRED, Sep 2026), up 44.8% in a year, and U.S. industrial electricity averages 9.64 cents per kWh. Both feed electrified-hardware unit economics.
  • The U.S. has 8,825 medical equipment and supplies establishments employing about 308,388 workers (Census County Business Patterns, 2023).

Common questions

  • What are safety stock days? Extra days of consumption held against demand spikes and late deliveries. Eight days on six parts a day is 48 parts.
  • How do I set the lead time? Measure from order to receipt on recent orders, including customs and inspection. Quoted lead times are usually shorter than measured ones.
  • What replaced the V1 multiplier? V1 scaled lead-time demand by a factor such as 1.1. V2 states the safety stock in days of demand, which you can measure and defend.
  • Does the result include parts on order? No. Add open orders due before the stockout date to the parts on hand when checking coverage.

Last reviewed 2026-10-28.