Microgrid Benchmarks

Microgrid Equipment KPIs: Benchmarks for Build, Test and Commissioning

Build hours, factory acceptance test yield, kit completeness, commissioning and interconnection: how to measure each KPI, what moves it, and which figures have a cited source.

† marks a figure with no cited source: it is kept as originally published and is illustrative. How the figures are sourced

Use these benchmarks as reference points for spotting a gap, not as targets. Measure weekly, post the numbers on the floor, and compare actuals with your own estimates while each job is still open and correctable.

Every figure shows its basis. A superscript number links to a public source in the Sources list, and the sentence gives that source's scope. A figure marked no cited source is kept exactly as originally published because no public source stating it was found, so treat it as illustrative.

At a glance

Microgrid equipment KPI benchmarks at a glance
KPITypicalStrongBasis
Assembly hours per metal-clad switchgear section38 to 48 (typical shops)28 to 32 (world class)†
Terminations landed and torqued per hour6 to 8 (average)10 to 14 (strong)†
First-pass FAT yield, test points passing80 to 88%92 to 97% (world class)†
FAT findings per switchgear section1.5 or more (signals process drift)Fewer than 0.5 (excellent)†
Kit completeness at mobilization88 to 94%98 to 100% verified (world class)†
I/O points commissioned per engineer per dayBelow 25 (signals integration problems)40 to 70 (seasoned team)†
Milestone dates commissioned on plan65 to 75%90% (world class)†
Protection relays tested per day, two-technician team6 to 10Not stated†
Relay test reworkOver 15% (settings or CT ratios wrong)Under 5% (world class)†
Interconnection, systems under 50 kWMedian 11 to 88 days (three states, 2022)Not statedDOE i2X roadmap1
Interconnection, systems of 50 kW and largerMedian 62 to 291 days (two states, 2022)Not statedDOE i2X roadmap1
Interconnection when a full impact study triggers6 to 12 monthsNot stated†
Words in parentheses give each figure's original framing or the source's scope. Not stated means the original guide gave no figure for that column. The interconnection medians are state data for 2022 from California, Massachusetts and New York, not national figures1.

Method: How the figures in this guide are sourced

A figure with a superscript number is stated by the cited source, listed under Sources with its publisher, location in the document and access date, and the sentence gives its scope. A figure marked no cited source is kept exactly as originally published because no public source stating it was found. It is illustrative, not measured industry data. Worked examples show arithmetic only and are not benchmarks.

Switchgear assembly hours

Shop labor productivity is the anchor KPI. World-class metal-clad switchgear assembly runs 28 to 32 hours per section†; typical shops sit at 38 to 48†, and troubled jobs exceed 55†.

Terminations per hour is the sub-metric: 10 to 14 landed and torqued terminations per hour is strong, and 6 to 8 is average†. Hold build-hour variance inside plus or minus 8 percent job over job to keep the estimate credible†.

For example, if the estimate is 34 hours per section and the job burns 46, the overrun is 46 / 34 = 1.35, or 35 percent, a gap that points to fixturing or drawing errors.

How to measure

  • Clock actual hours per completed section, not estimated hours.
  • Count terminations landed and torqued per clocked hour.
  • Compare actual with estimated hours on every job.

What moves it

  • Fixtured, kitted workstations, which cut switchgear build hours 15 to 25 percent†.
  • Accurate drawings, so wiring is not reworked on the bench.
  • Actual hours fed back into the estimate after every job, which tightens estimates until variance sits inside 8 percent†.

Compare actuals with the estimate from the Switchgear Assembly Hours calculator.

First-pass factory acceptance test yield

First-pass factory acceptance test (FAT) yield tells you how clean the build is. World class is 92 to 97 percent of test points passing on the first run†; typical is 80 to 88 percent†.

Count defects per unit at FAT too: fewer than 0.5 findings per switchgear section is excellent, and 1.5 or more signals process drift†. Every point failed at FAT is roughly 10x cheaper to fix in the shop than the same defect found in the field†, so protect this number.

Energy throughput matters as well. The Factory Acceptance Test Energy calculator sets the expected kWh, and a full-load run should complete inside 1.2x that budget†.

How to measure

  • Divide test points passed on the first run by total test points.
  • Count FAT findings per switchgear section.
  • Log full-load test energy against the calculated budget.

What moves it

  • A design-for-test checklist and a pre-FAT continuity sweep, which lift first-pass yield 5 to 10 points†.
  • Fixing the top root cause of findings before the next build starts.

Kit completeness at mobilization

Material readiness at mobilization drives field productivity. World-class cable and accessory kit completeness is 98 to 100 percent verified before the crew leaves the shop†; typical is 88 to 94 percent†.

Each missing item costs a half-day of crew idle at 3,000 to 5,000 dollars†. Aim for zero field-discovered shortages per project†.

Shops that hit 99 percent kit completeness cut field labor overruns from the typical 15 percent down to about 5 percent†.

How to measure

  • Verify every kit against the cable schedule with a hard checklist, not a glance.
  • Record completeness as verified items over required items at mobilization.
  • Count the shortages discovered in the field on every project.

What moves it

  • Barcoded kit verification, which takes completeness from 90 to 99 percent†.
  • A checklist that names every lug, gland and terminator line by line.

The Cable Kit Completeness calculator flags missing lugs, glands and terminators against the cable schedule.

Commissioning rate and schedule adherence

Commissioning points per day measures controls and startup efficiency. A seasoned team checks out 40 to 70 I/O points per day per engineer on a microgrid controller†; below 25 signals integration problems or a bad point list†.

Track schedule adherence as the share of milestone dates commissioned on plan. World class hits 90 percent of milestone dates†, and typical hits 65 to 75†.

Slippage compounds, because interconnection witness tests are scheduled with the utility and a missed date can cost weeks of delay.

How to measure

  • Count I/O points checked out per engineer per day.
  • Mark each milestone on plan or late against the baseline schedule.

What moves it

  • Pre-loaded and simulated controls point lists, which raise commissioning throughput about 30 percent†.
  • A clean, verified point list before the team reaches the site.

Size the point count and set a realistic daily rate and end date with the Controls Commissioning Load calculator.

Protection relay testing

Protection relay testing capacity governs energization readiness. A two-technician team tests 6 to 10 relays per day, including functional and pickup checks†.

World-class relay test rework is under 5 percent†. Anything over 15 percent means settings files or current transformer (CT) ratios are wrong†.

How to measure

  • Count relays fully tested per technician-day.
  • Divide relays retested by relays tested for the rework rate.

What moves it

  • Settings files checked before the test window opens.
  • CT ratios confirmed against the drawings before testing starts.

Convert relay count into technician-days and staff the window with the Protection Relay Test Capacity calculator.

Interconnection review turnaround

Utility interconnection approval often sets the energization date. A 2025 U.S. Department of Energy (DOE) roadmap reports that in 2022, median interconnection times for systems smaller than 50 kW ranged from 11 to 88 days across California, Massachusetts and New York1.

Larger systems wait longer. For systems of 50 kW and larger in California and Massachusetts, 2022 medians ranged from 62 to 291 days, in data that includes projects above 5 MW1. Plan a microgrid in that size class against these longer medians.

Expect 6 to 12 months when a full impact study triggers†. DOE's 2030 target is a median under 75 days from request to agreement for systems of 50 kW to 5 MW that do not trigger upgrades, a goal rather than current performance1.

How to measure

  • Date each submission and each utility response.
  • Count the days from request to a signed interconnection agreement.
  • Track projects that trigger a study separately from those that do not.

What moves it

  • Complete, accurate submissions the first time.
  • A schedule that plans for a full impact study whenever one is likely.

Size the review hours with the Grid Interconnect Review Load calculator.

How to build your own baseline

The gap between the typical and world-class bands is usually 30 to 50 percent of avoidable cost and schedule†. Standardize before you automate, and work on one KPI at a time.

  • Measure every KPI weekly and post the numbers on the floor.
  • Compare actuals with the Switchgear Assembly Hours and Field Install Labor estimates while each job is still open.
  • Pick the KPI with the widest gap to world class and fix its top root cause.
  • Feed actual hours back into both estimates after every job.
  • Move to the next KPI once the first one holds.

Sources

  1. Distributed Energy Resource Interconnection Roadmap: Transforming Interconnection by 2035 (PNNL-35696). U.S. Department of Energy, Interconnection Innovation e-Xchange (i2X); Pacific Northwest National Laboratory. published January 16, 2025. Printed p. 25, Table 1 2030 targets and text on 2022 medians for systems under 50 kW; printed p. 26, 2022 medians for systems of 50 kW and larger. Accessed September 30, 2026.

Published 2026-07-02.