Production and Throughput

Job Dispatch List Excel Template

Rank every open job at each work centre by critical ratio, due date, slack or shortest job, see which jobs will finish late, and print the run order for each machine.

Free, and a plain .xlsx with no macros to enable. A CSV with live formulas and a printed how-to guide come with it.

Overview

This job dispatch list is a working Excel workbook for schedulers, supervisors and owners of job shops who need to decide which job runs next on each machine. It ships with 30 open jobs at five work centres of a fictional machine shop, so the run orders, expedite list and charts are populated the moment you open it; replace the example rows with your own and everything recalculates.

Each row is one open job at the work centre it is waiting at. The workbook adds up the hours still needed, here and at the later operations, and counts the working hours until the due date from the status date with Excel's NETWORKDAYS, skipping weekends and your holidays. The critical ratio is the hours until due divided by the hours remaining, the same formula as the Job Dispatch Critical Ratio calculator on this site, with slack and projected lateness beside it. Each work centre's queue is then ranked by the rule you choose on Setup.

In practice, update the status date and the open jobs each morning, print the dispatch list for each machine and work the expedite list from the top. The Dashboard shows where the work is queued: in the example the mill holds 14.5 days of work and six of its thirteen jobs are behind schedule, which no run order can fix without overtime, a split or a new promise date.

What this template includes

Suggested use case

Use it in the morning production meeting to set each machine's run order, to build the expedite list, and to see which promise dates cannot be met before the customer calls.

How to use it

  1. On Setup, enter your shop name, the status date, the hours worked per day and your dispatch rule, then replace the example work centres and holidays.
  2. On Open Jobs, add one row per job at the work centre it is waiting at: quantity, setup and run time, hours of the later operations and the due date.
  3. Fix anything the Check column flags, then read the Status column: Overdue and Below target jobs need expediting or a new date.
  4. On Dispatch List, pick a work centre and print its run order for the machine.
  5. Update the status date and the open jobs each morning; the ratios, run orders and Dashboard update themselves.

Frequently Asked Questions

How is the critical ratio calculated?
Critical ratio = working hours until the due date / production hours still needed. The calculator's example has 16 hours until due and 12 hours of work: a ratio of 1.33 and 4 hours of slack. Under 1 the job finishes late at standard times: in the example, job J-24120 at the mill has 32 working hours until due and 55 hours of work left, a ratio of 0.58 and a projected 23 hours late.
How are the hours until due worked out?
From the start of the status date to the end of the due date, in working days times the shop's hours per day, skipping Saturdays, Sundays and the holidays on Setup. As of Monday 23 November at 16 hours a day, a job due Tuesday 24 November has 2 working days, 32 hours; Thanksgiving and the day after are not counted. A job due the previous Thursday has -16 hours: the Friday since was a working day.
Which dispatch rule should I use?
Critical ratio weighs the due date against the work left, so a big job due Tuesday outranks a small one due the same day. Earliest due date is the simplest to explain on the floor; on a single machine it gives the smallest maximum lateness. Shortest job first gives the lowest average time jobs spend waiting on a single machine, but can leave long jobs waiting. Least slack ranks by hours to spare. Change the rule on Setup and every run order updates.
Why is a job with a ratio above 1 still marked Due soon?
Because it has little slack. Jobs with a critical ratio from 1 up to the limit on Setup (1.2 in the example) show Due soon: job J-24142 at the mill, at 1.01, has 0.3 hours to spare, so one breakdown or a late material delivery makes it late.
Does the dispatch list check capacity?
No. A run order decides which job goes first, not whether every date can be met. The Dashboard's days of work queued shows the gap: in the example the mill holds 231.4 hours, 14.5 days at 16 hours a day, with jobs due this week, so some dates need overtime, a split order or a new promise whatever the order.