Production and Throughput

Machine Utilization Tracker Excel Template

Log each machine's day in hours and see utilization, idle time, downtime and the reasons machines sit idle, by machine, day and week.

Free, and a plain .xlsx with no macros to enable. A CSV with live formulas and a printed how-to guide come with it.

Overview

This machine utilization tracker is a working Excel workbook for production managers, schedulers and plant managers who need to know which machines are earning their floor space. It ships with four weeks of example data for a fictional six-machine CNC shop, so the dashboard and charts are populated the moment you open it; replace the example rows with your own and everything recalculates.

Each row is one machine-day. You type the hours the machine was available, then how many it ran, how many it was down for faults and repairs, and how many it sat idle, with the main reason it was idle. The workbook calculates the unassigned remainder, utilization (run hours over available hours), and the idle and downtime shares, the same formulas the Machine Utilization calculator on this site uses for a single day. Every roll-up adds hours before it divides, so utilization for a machine, a week or the whole shop is never an average of percentages.

In practice, fill in each machine's day at the end of the shift and review the dashboard weekly. Utilization by machine shows which machines are overloaded and which have room; the where-available-time-went chart separates downtime (a maintenance problem) from idle time (an orders, staffing, setup or material problem); and the idle-hours Pareto tells you which of those to work on first.

What this template includes

Suggested use case

Use it to see which machines are busy and which sit idle before you buy, move or retire a machine, to plan staffing and setups, or to report machine-hours in a weekly production review.

How to use it

  1. On Setup, enter your plant name and utilization target, then replace the example machines and idle reasons with your own.
  2. On Machine Log, add one row per machine per day with its available hours and the hours it ran, was down and sat idle.
  3. Pick the main idle reason for any day with idle hours, and fix anything the Check column flags.
  4. Open the Dashboard and filter by machine or dates to review one machine, one week or the whole shop.
  5. Use the idle-hours Pareto to decide what to fix first: orders, setups, staffing or material.

Frequently Asked Questions

How is machine utilization calculated?
Utilization is run hours divided by available hours. A machine available for 16 hours that ran 11.5, was down 1.2 and sat idle 3.3 is 71.9 percent utilized, with a 20.6 percent idle share and a 7.5 percent downtime share, the same answer as the Machine Utilization calculator. Over several days the workbook adds the run hours and the available hours first, then divides.
What should count as available hours?
The hours the machine could have run that day: the shifts it was scheduled or staffed for, or 24 if it runs round the clock. A two-shift machine is usually 16 available hours. Planned maintenance inside those hours is downtime; if you plan it outside them, leave it out of available hours instead.
Is setup time idle time or run time?
In this workbook setup is idle time, because the machine is not making product, and it is filed under the Setup and changeover reason. Four hours of setup in a 16-hour day takes 25 points off that day's utilization, so the idle-hours Pareto shows you when shorter setups would free the most capacity.
What is the difference between utilization and OEE?
Utilization says how busy a machine was; OEE says how well it ran while it was meant to be running, including slow cycles and scrap. A machine can run 20 of 20 available hours (100 percent utilization) at an OEE of 60 percent if it runs slowly or makes scrap. Use this tracker to find idle capacity and the OEE Tracker to find speed and quality losses.
What utilization target should we set?
Set your own on the Setup sheet; the workbook does not assume an industry benchmark. A bottleneck machine is often worth running close to its available hours, while a machine you keep for flexibility may sit lower on purpose. With a 75 percent target, a machine at 71.9 percent shows Near target and one at 50.5 percent shows Below target, 24.5 points short.