Planning and Supply Chain
Master Production Schedule Excel Template
Plan each finished item week by week from forecast and customer orders, and see the MPS receipts, the projected available balance and how many units are still free to promise.
Free, and a plain .xlsx with no macros to enable. A CSV with live formulas and a printed how-to guide come with it.
Overview
This master production schedule is a working Excel workbook for master schedulers, planners and the sales and customer-service teams who quote delivery dates. It ships with 12 weeks of example data for four pump models at a fictional pump maker, Christmas dip included, so the MPS record, the promise check and the charts are populated the moment you open it; replace the example rows with your own and everything recalculates.
Each row is one item in one week. You type the forecast, the customer orders booked and any lot already firmed; the workbook works out the demand to plan against (orders only inside the demand time fence, the larger of forecast and orders beyond it), plans whole lots whenever the projected available balance would fall below safety stock, and works out available to promise: on hand plus MPS to date, less customer orders to date, safety stock and stock on hold, as the Available to Promise calculator on this site does, then the lowest of that from the week on, so a new promise never takes stock a later order needs.
In practice, run it before the weekly scheduling meeting: approve or move the lots flagged inside the fence, check the projected available line against safety stock, and use the promise check whenever sales asks for a date. In the example, 50 pumps for the week of 7 December cannot be promised: only 34 are free until the next lot lands in the week of 28 December.
What this template includes
- MPS Plan sheet: one row per item per week with forecast, customer orders booked and any MPS quantity already firmed
- Demand by your demand time fence (customer orders inside it, the larger of forecast and orders beyond it) and planned MPS lots that keep the projected available balance at or above safety stock
- Available to promise for every item and week: the stock not needed for booked orders, safety stock or stock on hold, never taken from a later order
- Fence column that flags a new lot planned inside the demand time fence, and a Check column for weeks that are not plan Mondays, duplicate rows and unknown items
- Dashboard promise check: pick an item, a week and a quantity and see whether it can be promised and how many units short it is
- The classic MPS record for any item (forecast, orders, demand, firm and planned MPS, projected available, ATP, safety stock) plus ATP and projected available for every item and week, with two native charts
- Method sheet with every formula, a Verify sheet that re-checks them against an independent reference (Self-check: PASS), and an About MFG Calcs sheet linking the live Available to Promise calculator and every free tool on the site
Suggested use case
Use it in the weekly master scheduling or S&OP meeting to set the build plan, to answer sales when a customer asks for a delivery date, and to see which lots break the frozen zone before they reach the floor.
How to use it
- On Setup, enter the plan start (a Monday) and your demand time fence, then replace the example items with your on-hand stock, safety stock, lot size and stock on hold.
- On MPS Plan, give each item one row per week with its forecast, the customer orders booked and any MPS quantity already firmed.
- Fix anything the Check column flags, then approve or move every lot the Fence column marks Check.
- On the Dashboard, pick an item, a week and a quantity to see whether it can be promised.
- Each week, roll the plan start forward, add the new week and update orders and firmed lots.
Frequently Asked Questions
- How is available to promise calculated?
- On hand plus MPS receipts to date, minus customer orders to date, safety stock and stock on hold; then the lowest of that balance from the week on, never below zero. The Available to Promise calculator's example has 1,800 units of supply, 940 committed, 250 of safety stock and 80 on hold: 1,800 - 1,270 leaves 530 to promise, so a new order of 500 fits.
- Why can I promise only 34 when 131 are projected available?
- Projected available is stock after forecast demand; available to promise is stock not already sold. For the 50 mm pump in the week of 7 December: 140 on hand + 120 from the firmed lot - 186 ordered through Christmas week - 40 safety stock = 34. A 50-unit order would take pumps already promised to later customers, so the check says No, 16 short, until the next lot of 120 lands in the week of 28 December.
- What does the demand time fence do?
- Inside it, the plan uses customer orders only and treats the schedule as frozen; beyond it, demand is the larger of forecast and orders. A lot planned inside the fence shows Check: in the example the 80 mm pump needs a lot of 60 in week 2, inside the 3-week fence, so someone must approve it, expedite it or let a customer date move.
- How does the plan decide when to make a lot?
- Whenever the projected available balance would drop below safety stock, it plans enough whole lots to stay above it. The 50 mm pump ends the week of 21 December at 59; the next week's demand of 30 would leave 29, under the safety stock of 40, so a lot of 120 is planned that week and the balance ends at 149.
- Can I fix an MPS quantity by hand?
- Yes: type it in Firm MPS for that week and the plan counts it as supply, planning lots only for what it does not cover. In the example the gear pump's lot of 200 is firmed for the week of 7 December, so no new lot is planned until the balance would fall below its safety stock of 50 in the week of 11 January.