Purchase Order Tracker Excel Template

Track every purchase order line from order to receipt and see each supplier's on-time delivery, the lines that are overdue or promised too late, open PO value by week and the lines to chase first.

Free, and a plain .xlsx with no macros to enable. A CSV with live formulas and a printed how-to guide come with it.

Overview

This purchase order tracker is a working Excel workbook for buyers, purchasing managers and production planners. It ships with 140 purchase order lines from a fictional maker of hydraulic cylinders and six suppliers, so every chart and table is populated the moment you open it; replace the example rows with your own and everything recalculates.

Each row is one PO line. You type what was ordered, from whom, when you need it and, as they happen, the date the supplier promised and the date and quantity received. The workbook works out the due date, flags lines that are overdue or promised later than you need them, asks for a date on POs nobody has confirmed, and scores every received line as on time or not inside the window you set, the same measure as the Supplier On-Time Delivery calculator on this site.

In practice, keep the sheet open while you buy: the chase list says which lines to call about first, the supplier table shows whose promises hold, and the weekly chart shows how much purchase value is due to arrive, and be paid for, in the next eight weeks.

What this template includes

Suggested use case

Use it every day to chase the right lines and every month to review suppliers: what is overdue, which POs still have no promised date, which suppliers miss their own promises and how much money is due to arrive in the coming weeks.

How to use it

  1. On Setup, enter your company name, currency, status date, on-time target and on-time window, then replace the example suppliers and buyers.
  2. On PO Lines, add one row per purchase order line with its supplier, item, quantity, unit price, order date and need date.
  3. When the supplier confirms, type the promised date; when goods arrive, type the received date and the quantity received.
  4. Update the status date when you review, fix anything the Check column flags and work the Action column.
  5. Open the Dashboard and filter by supplier, buyer or due dates; chase the lines at the top of the list first.

Frequently Asked Questions

How is supplier on-time delivery calculated?
Lines received on time divided by lines received, times 100. The example received 115 lines in full, 85 of them inside the window: 73.9 percent against a 95 percent target, so 25 more on-time lines would have been needed. The Supplier On-Time Delivery calculator's example, 188 on time out of 200, is 94 percent: 4 points short of 98 percent, or 8 more on-time deliveries.
Should early deliveries count as on time?
Set the window on Setup: the example accepts up to 3 days early and none late. Early stock ties up cash and space, so the window matters: Crayke Fasteners was never late in the example, but 5 of its 22 lines arrived more than 3 days early, which puts it at 77.3 percent.
Which date should on-time delivery use: need date or promised date?
The promised date, because that is the supplier's own commitment; the need date applies until a date is promised. The workbook also shows how many days later than needed each line was promised, and marks those lines Expedite even before they are late.
Which purchase order lines should I expedite first?
The Dashboard lists the lines that need action by due date. In the example 3 lines are overdue, 6,674 in value, led by two position-sensor lines from Embsay Electronics, the supplier with the worst record: 4 of 9 lines on time and 16.8 days late on average. Three recent POs have no promised date yet and are marked Ask for a date.
What does open PO value by week show?
The purchase value still to be received, grouped by the week each line is due: a view of the deliveries, and the bills, coming in. The example has 80,262 open, with 22,042 due in the week of the status date and 12,665 the week after.