Quote Engineering Workload Planner Excel Template

Log every RFQ, see the engineering hours the open ones need by the week they are due against the hours your team has for quoting, and track how many quotes go out on time.

Free, and a plain .xlsx with no macros to enable. A CSV with live formulas and a printed how-to guide come with it.

Overview

This quote engineering workload planner is a working Excel workbook for quoting and estimating managers, engineering managers and owners of job shops and contract manufacturers who quote technical RFQs. It ships with ten weeks of example RFQs at a fictional contract machine shop, so the dashboard, plan and charts are populated the moment you open it; replace the example rows with your own and everything recalculates.

Each row is one RFQ. An RFQ that needs an engineer to read a drawing, choose a process or estimate a cycle time takes engineering review hours; a catalogue item priced from a rate card takes none. Each complexity class carries the hours an RFQ of that kind takes, from your time tickets, and a big RFQ can carry its own estimate. The workbook adds up the open RFQs by the week they are due and sets them against the hours your team has for quoting after meetings and interruptions, so a week that cannot be covered stands out before it arrives.

The open pipeline is also split the way the Engineering Quote Burden calculator on this site splits a batch of RFQs: the gross hours requested, the hours lost because engineering is not fully available for quoting, the hours at risk of rework when a quote is challenged, and the usable hours that remain. The calculator stops at usable hours; this workbook schedules them against the calendar and tracks how many quotes go out by their due date.

What this template includes

Suggested use case

Use it to see a week of RFQs coming that your quoting engineers cannot cover in time, to decide which RFQs to decline, simplify or move, and to report quote turnaround and on-time performance.

How to use it

  1. On Setup, enter the status date, your engineering availability for quoting and quote reuse and confidence, then your complexity classes with their engineering hours per RFQ and your engineers with their quoting hours a week.
  2. On RFQ Log, add one row per RFQ: received, RFQ number, customer, whether it needs engineering review, its class or an hours estimate, due date, engineer and status.
  3. When a quote goes out, set the status to Quoted and type the date; set declined and no-bid RFQs so they stop counting.
  4. Fix anything the Check column flags.
  5. On the Dashboard, look for weeks over capacity, the RFQs past due and each engineer's open hours, and track on-time quoting week by week.

Frequently Asked Questions

How many engineering hours do our RFQs need?
Give each complexity class the engineering review hours an RFQ of that kind takes, from your time tickets, and type an estimate for any RFQ far from its class. The workbook adds the hours of every open technical RFQ: in the example, 18 open technical RFQs need 105.5 hours, an average of about 5.9 hours each.
How do I know if a week is over capacity?
Compare the hours requested by RFQs due that week with the hours your team really has for quoting: the sum of each person's quoting hours a week times engineering availability. In the example the team has 50 hours a week at 90% availability, 45 hours; three conveyor RFQs due the week of 7 December need 48 hours, a load of 107%, so that week needs help, a later due date or a decline.
What are hours lost to availability and hours at risk?
They are the Engineering Quote Burden calculator's split of the hours requested. Availability loss is time the team cannot give to RFQ review at all: 105.5 hours x 10% = 10.55 hours in the example. Hours at risk are spent but may be redone when a quote is challenged or repriced: the 94.95 available hours x 15% = 14.24 hours. The usable hours that remain are 80.71.
How do I track quote turnaround?
Type the date each quote goes out. Days to quote is that date less the date received, and a quote is on time when it goes out by its due date. In the example 51 of 57 dated quotes went out on time (89.5%), at an average of 11.1 days from receipt; the chart shows on-time and late quotes for each of the last eight weeks.
Should catalogue or repeat RFQs count?
Only if they need an engineer. A repeat part at a new quantity can often be repriced from the last quote by an estimator, so mark it Technical: No and it takes no engineering hours; if it needs a drawing check, mark it Yes and give it its class's hours, half an hour in the example.