Maintenance and Reliability

Repair or Replace Equipment Analysis Excel Template

Compare repairing and keeping an ageing machine with replacing it, year by year and in present value, with the equivalent annual cost of each, the break-even year and the simple payback.

Free, and a plain .xlsx with no macros to enable. A CSV with live formulas and a printed how-to guide come with it.

Overview

This repair or replace equipment analysis is a working Excel workbook for maintenance and reliability managers, plant engineers and finance teams facing the classic question: the old machine needs a big repair, so do we fix it or replace it? It ships with a worked example, a 19-year-old rotary screw air compressor whose airend is failing, so every figure, chart and verdict is populated the moment you open it; overwrite the yellow cells with your asset and everything recalculates.

Both options go on one timeline. Year 0 holds the repair needed now, or the replacement's price and installation less what the old asset fetches. Each later year holds the option's maintenance, unplanned downtime at your cost per hour, and energy, with the old asset's maintenance and downtime growing each year as it ages, overhauls typed in the year they are planned, and end values credited in the last year. Discounting at your rate gives each option's present-value cost; the difference is the net present value of replacing, and the equivalent annual cost spreads each option evenly over the horizon.

A simple screen with year-1 costs held constant gives the same payback, net benefit and ROI as the Asset Replacement Payback calculator on this site, and the build checks the workbook against it. The dashboard adds the break-even year, a cumulative cost chart and where the difference comes from: maintenance, downtime, energy, the money spent now and the end values.

What this template includes

Suggested use case

Use it when an ageing machine needs a major repair and you have to decide, and justify, whether to repair and keep it or replace it, for a capital request or a maintenance budget review.

How to use it

  1. On Setup, enter your company name, currency, discount rate and the cost of an hour of downtime on this asset.
  2. On Comparison, describe the asset, then enter the repair needed now and the old asset's year-1 maintenance, downtime and energy, how fast they grow and its end value.
  3. Enter the replacement: price, installation, trade-in, its year-1 maintenance, downtime and energy, a yearly increase and its residual value.
  4. On Year by Year, keep one row per year of the horizon and type any overhaul or major work planned for either option in its year.
  5. Open the Dashboard to read the net present value of replacing, both equivalent annual costs, the break-even year and the simple payback.

Frequently Asked Questions

How do I decide whether to repair or replace a machine?
Compare the total cost of each option over the same horizon, in present value. In the example, rebuilding the old compressor and running it for 8 years costs 513,346 in present value at a 10% discount rate, and replacing it costs 339,086, so replacing has a net present value of 174,260 even though it costs 78,000 more today.
What is equivalent annual cost?
The present-value cost of an option spread into equal yearly amounts over the horizon: PV x r / (1 - (1 + r)^-n). It lets you compare options as a cost per year. In the example, keeping the old compressor is 96,224 a year and replacing it 63,560 a year over 8 years at 10%.
How is the simple payback of a replacement calculated?
Divide the extra investment by the yearly savings. Replacing costs 96,000 + 14,000 installation - 4,000 trade-in - the 28,000 rebuild it avoids = 78,000 more now; it saves 77,000 - 45,900 = 31,100 a year in maintenance, downtime and energy, so it pays back in 2.51 years. The Asset Replacement Payback calculator gives the same answer.
How should downtime be counted?
Multiply the unplanned downtime hours a year by what an hour of downtime costs you: lost contribution, overtime, scrap and expediting. The example's old compressor loses 30 hours in year 1 at 650 an hour, 19,500, and its downtime grows 12% a year as it ages. Use 0 for the cost per hour if a standby machine takes over.
What if a major overhaul is due in a later year?
Type it on the Year by Year sheet in the year it is planned, for either option: the example has a 6,500 motor rewind on the old compressor in year 4 and a 4,200 airend service on the new one in year 5. Both are discounted with that year's costs and show in the cumulative cost chart.