Rework and Sort Cost Log Excel Template
Log every rework and sort job and see what it costs in labour, material and charges, by cause, part, source and week, and what suppliers paid back.
Free, and a plain .xlsx with no macros to enable. A CSV with live formulas and a printed how-to guide come with it.
Overview
This rework and sort cost log is a working Excel workbook for quality managers, plant managers, supplier quality engineers and cost accountants who need rework, sorting and containment in money, not just in hours. It ships with twelve weeks of example jobs for a fictional automotive supplier, so the dashboard and charts are populated the moment you open it; replace the example rows with your own and everything recalculates.
Each row is one job: a rework, a sort or a containment action on one part for one cause. You type how many units were handled, the person-minutes each took and the labour type, plus any extra material, machine or booth time and repeat inspection charged to the job. The workbook prices it the same way the Rework Cost calculator on this site does, labour hours times the loaded rate plus material and charges, and gives the cost per unit, the net cost after anything a supplier or customer paid back, and the share of sorted units found bad.
In practice, log each job when it closes and review the dashboard weekly. The cost-by-cause Pareto shows which problems cost the most; the by-source chart separates what your own processes cost from what suppliers and customers caused, and how much of it came back; and cost by part tells you where a permanent fix pays for itself fastest.
What this template includes
- Rework Log table: one row per rework, sort or containment job with units handled and rejected, person-minutes per unit, labour type, extra material, machine and inspection charges and any amount recovered
- Per-job labour hours, labour cost at the labour type's loaded rate, material cost, total cost, cost per unit, net cost after recoveries and reject rate
- Check column that names problems in words: more units rejected than handled, a recovery larger than the cost, a part, cause or labour type not on the Setup lists
- Dashboard with part, cause and date filters and eight KPI tiles, including total cost, cost net of recoveries, labour hours, cost per unit and the costliest cause
- Four native charts: cost by week split into labour, material and charges, a cost-by-cause Pareto, cost by part, and cost and recoveries by source (internal, supplier, customer)
- By-source, by-part and weekly tables that add money and hours first and divide last
- Method sheet with every formula, a Verify sheet that re-checks them against an independent reference (Self-check: PASS), and an About MFG Calcs sheet linking the live calculator and every free tool on the site
Suggested use case
Use it to put a number on rework and containment sorting for a quality review, to back up a supplier chargeback with the hours and charges behind it, or to see which causes and parts to fix first.
How to use it
- On Setup, enter your plant name and currency, then replace the example labour types (with your loaded rates), parts and causes.
- On Rework Log, add one row per rework or sort job: units handled, person-minutes per unit, labour type, and any material, machine or inspection charges.
- When a supplier or customer pays some of it back, type the amount in Recovered on the job it covers.
- Fix anything the Check column flags, then open the Dashboard and filter by part, cause or dates.
- Use the cost-by-cause Pareto to choose what to fix first, and the by-source table to see what is still to recover.
Frequently Asked Questions
- How is the cost of a rework job calculated?
- Labour hours are units handled times person-minutes per unit divided by 60, and labour cost is those hours times the loaded rate. Material, machine charges and repeat inspection are added on top. Reworking 80 units at 6 minutes each is 8 hours; at 38 an hour that is 304.00, plus 1.20 of material per unit (96.00), for a total of 400.00, or 5.00 per unit, the same answer as the Rework Cost calculator.
- How do I enter a sort that several people worked on?
- Turn the hours into person-minutes per unit: people times hours times 60, divided by the units sorted. Three people sorting 2,000 housings for 6 hours is 3 x 6 x 60 / 2,000 = 0.54 minutes per unit. For a sort that runs over several days, add one row per day so the weekly figures stay right.
- How do I record a supplier chargeback?
- Type what the supplier paid back or credited in the Recovered column of the job it covers. A sort of 500 units at 0.5 minutes and 30 an hour (125.00 of labour) with 150.00 of machine time and 90.00 of inspection costs 365.00; if the supplier pays 200.00, the net cost is 165.00. The by-source table shows the share recovered for supplier, customer and internal causes.
- What loaded labour rate should I use?
- Use your own costing: the hourly wage plus benefits, payroll taxes and the overhead your plant charges to labour. Contract sorters billed by the hour are a labour type of their own at their invoiced rate. The rates in the example are examples only; the workbook does not assume an industry figure.
- Should idle machine time count as a rework cost?
- Only charge machine time that was actually spent or billed on the job. Like the Rework Cost calculator, the workbook does not assume that occupied capacity would otherwise have made sales; if a sort really displaced paid production, enter that cost as a machine charge and say why in the notes.